Permit Details

Permit Search

Permit

New Residential Construction

210 SW BLUEBERRY PL
LAKE CITY, FL 32024

Permit #
000037565
Application #
40040
Status Completed
  1. Submitted Dec 20, 2018
  2. Issued Dec 20, 2018
  3. Expires Oct 20, 2019
  4. Completed Apr 26, 2019

Property

Parcel #
03121-057
Owner
Deborah Winner-hall
Acres
0.61
Subdivision
Piccadilly Park
Zoning
RSF-2
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0381D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1875.00
Total Area (Sqft)
2925.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0930

Status & Review History

No status updates yet.

Contractors

  • B. Trent Giebeig

    License
    CRC1330693
    Title
    —
    Role
    —

Inspections

  1. Dec 26, 2018

    Passed: Building - Footer

    Inspected by Randy Jones

  2. Dec 26, 2018

    Passed: Engineering - Setbacks

    Inspected by Randy Jones

  3. Dec 26, 2018

    Cancelled: Electrical - Temporary Service

    Inspected by Randy Jones

  4. Dec 31, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  5. Jan 3, 2019

    Passed: Building - Slab

    Inspected by Troy Crews

  6. Feb 6, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  7. Feb 6, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  8. Feb 18, 2019

    Failed: Building - Framing

    Truss T28 Needs Brace As Called For On Truss Drawings anchor Bolt Missing At Front Window also Missing On East Side Of Garage.

    Inspected by Tommy Matthews

  9. Mar 1, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  10. Mar 1, 2019

    Failed: Mechanical - Rough In

    Stove Vent Not Complete

    Inspected by Troy Crews

  11. Mar 1, 2019

    Rescheduled 3/4/2019:Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Troy Crews

  12. Mar 1, 2019

    Rescheduled 3/4/2019:Plumbing/Gas - Rough In

    Inspected by Troy Crews

  13. Mar 1, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  14. Mar 4, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  15. Mar 4, 2019

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Troy Crews

  16. Mar 4, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  17. Mar 7, 2019

    Passed: Building - Insulation

    Inspected by Tommy Matthews

  18. Apr 9, 2019

    Failed: Electrical - Permanent Power

    Need Locks

    Inspected by Tommy Matthews

  19. Apr 10, 2019

    Release to power company

    Inspected by Lh

  20. Apr 10, 2019

    Passed: Electrical - Permanent Power

    Inspected by Tommy Matthews

  21. Apr 10, 2019

    Septic Release Inspection

    Inspected by Health Dept

  22. Apr 23, 2019

    Passed: Building - Final

    Inspected by Troy Crews