Permit Details

Permit Search

Permit

New Residential Construction

262 SW FOREST GLN
LAKE CITY, FL 32025

Permit #
000037505
Application #
39947
Status Completed
  1. Submitted Dec 3, 2018
  2. Issued Dec 3, 2018
  3. Expires Nov 27, 2019
  4. Completed Jun 3, 2019

Property

Parcel #
09116-117
Owner
Bradley & Sandra Ward
Acres
5.01
Subdivision
Hills @ Rose Creek
Zoning
PRRD
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0384D
This is the construction of a
SFD/UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
2061.00
Total Area (Sqft)
2961.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0874

Status & Review History

No status updates yet.

Contractors

  • S. Van Conner

    License
    CRC057203
    Title
    —
    Role
    —

Inspections

  1. Dec 3, 2018

    Release to power company

    Inspected by Troy Crews

  2. Dec 4, 2018

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  3. Dec 4, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  4. Dec 12, 2018

    Rescheduled 12/13/2018:Building - Monolithic Slab

    Not Ready

    Inspected by Laurie Hodson

  5. Dec 12, 2018

    Rescheduled 12/13/2018:Engineering - Setbacks

    Not Ready

    Inspected by Laurie Hodson

  6. Dec 12, 2018

    Cancelled: Engineering - Setbacks

    Inspected by Troy Crews

  7. Dec 13, 2018

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  8. Dec 13, 2018

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  9. Jan 7, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  10. Jan 7, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  11. Feb 15, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  12. Feb 15, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  13. Feb 15, 2019

    Failed: Mechanical - Rough In

    Bath Fan Ducts Pulled Loose And Drooping, Also Need To Complete Secondary Drain On Pan For Air Handler

    Inspected by Troy Crews

  14. Feb 15, 2019

    Cancelled: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  15. Feb 15, 2019

    Failed: Plumbing/Gas - Rough In

    Need To Insulate Water Lines Exposed To Soffit Area ,short Pieces

    Inspected by Troy Crews

  16. Feb 20, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  17. Feb 20, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  18. Mar 11, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  19. Apr 17, 2019

    Passed: Electrical - Permanent Power

    Need Septic And Driveway Release

    Inspected by Matt Forsyth

  20. Apr 29, 2019

    Septic Release Inspection

    Need Driveway Final

    Inspected by Health Dept

  21. May 3, 2019

    Release to power company

    Inspected by Lh

  22. May 31, 2019

    Passed: Building - Final

    Blower Door Test Recieved

    Inspected by Troy Crews