Status Completed
  1. Submitted Nov 13, 2018
  2. Issued Nov 13, 2018
  3. Expires Jan 19, 2020
  4. Completed Jul 30, 2019

Property

Parcel #
09116-129
Owner
Matthew Hentzelman
Acres
5.01
Subdivision
Hills At Rose Creek S/d
Zoning
AG-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0384D
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
2
Heated Area (Sqft)
3348.00
Total Area (Sqft)
4532.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0889

Status & Review History

No status updates yet.

Contractors

This is an owner-builder project.

  • Matthew Hentzelman

    License
    CGC1514780
    Title
    —
    Role
    —

    County License & State License Expired.

Inspections

  1. Dec 11, 2018

    Passed: Building - Footer

    Inspected by Tommy Matthews

  2. Dec 11, 2018

    Passed: Engineering - Setbacks

    Inspected by Tommy Matthews

  3. Dec 18, 2018

    Release to power company

    Inspected by Troy Crews

  4. Dec 19, 2018

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  5. Dec 26, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Randy Jones

  6. Dec 28, 2018

    Passed: Building - Slab

    Inspected by Randy Jones

  7. Mar 20, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  8. Mar 20, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  9. May 8, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  10. May 8, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  11. May 8, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  12. May 8, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  13. May 14, 2019

    Rescheduled 5/15/2019:Building - Insulation

    Inspected by Troy Crews

  14. May 15, 2019

    Rescheduled 5/16/2019:Building - Insulation

    Called Wants To Reschedule For 5/16/2019

    Inspected by Laurie Hodson

  15. May 16, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  16. Jul 12, 2019

    Passed: Electrical - Permanent Power

    Need Health Release

    Inspected by Troy Crews

  17. Jul 15, 2019

    Release to power company

    Rec'd Eh

    Inspected by Tc

  18. Jul 15, 2019

    Septic Release Inspection

    Inspected by Health Dept

  19. Jul 23, 2019

    Passed: Building - Final

    Inspected by Matt Forsyth