Permit Details

Permit Search

Permit

New Residential Construction

228 NW BROOK LOOP
LAKE CITY, FL 32055

Permit #
000037407
Application #
39799
Status Completed
  1. Submitted Nov 6, 2018
  2. Issued Nov 6, 2018
  3. Expires Mar 29, 2020
  4. Completed Oct 8, 2019

Property

Parcel #
02206-013
Owner
Daniel Schnabel
Acres
1.78
Subdivision
Fairfield Brooks
Zoning
A-3
Flood zone
A
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0280D
This is the construction of a
SFD/UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Heated Area (Sqft)
1447.00
Total Area (Sqft)
2225.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0680

Status & Review History

No status updates yet.

Contractors

  • Tabitha Sibel

    License
    CGC1515388
    Title
    —
    Role
    —

    County License & State License Expired.

Inspections

  1. Nov 14, 2018

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Nov 14, 2018

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Jan 4, 2019

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  4. Jan 4, 2019

    Release to power company

    Inspected by Troy Crews

  5. Jan 8, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  6. Jan 11, 2019

    Passed: Building - Slab

    Inspected by Troy Crews

  7. Jan 29, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  8. Feb 8, 2019

    Cancelled: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  9. Feb 8, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  10. Feb 8, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  11. Mar 29, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  12. Mar 29, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  13. Mar 29, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  14. Mar 29, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  15. Apr 9, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  16. Sep 4, 2019

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  17. Sep 9, 2019

    Release to power company

    Eh Rec'd.

    Inspected by Mtc

  18. Sep 9, 2019

    Septic Release Inspection

    Inspected by Health Dept

  19. Oct 1, 2019

    Passed: Building - Final

    Release Pending. Blower Door Test, Rec'd 10/8/19

    Inspected by Troy Crews