Permit Details

Permit Search

Permit

New Residential Construction

266 SW BEACON WAY
LAKE CITY, FL 32025

Permit #
000037405
Application #
39796
Status Completed
  1. Submitted Nov 5, 2018
  2. Issued Nov 5, 2018
  3. Expires Mar 17, 2020
  4. Completed Sep 26, 2019

Property

Parcel #
02951-107
Owner
Amelia Landing Inc
Acres
0.50
Subdivision
Amelia Landing
Zoning
PRD
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0293D
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1605.00
Total Area (Sqft)
2193.00
Building Code Occupancy Types
Residential
Occupancy Use Title
NEW HOME
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
X-CITY

Status & Review History

No status updates yet.

Contractors

  • Bradley Franks

    License
    R291103874
    Title
    —
    Role
    —

    County License & State License & Workers Comp Expired.

Inspections

  1. Nov 13, 2018

    Passed: Building - Footer

    Inspected by Randy Jones

  2. Nov 13, 2018

    Passed: Engineering - Setbacks

    Inspected by Randy Jones

  3. Nov 27, 2018

    Rescheduled 11/28/2018:Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  4. Nov 27, 2018

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  5. Nov 27, 2018

    Release to power company

    Inspected by Troy Crews

  6. Nov 28, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  7. Dec 4, 2018

    Passed: Building - Slab

    Inspected by Tommy Matthews

  8. Dec 13, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  9. Dec 27, 2018

    Passed: Building - Roof Decking

    Inspected by Tommy Matthews

  10. Jan 3, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  11. Jan 24, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  12. Jan 24, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  13. Jan 24, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  14. Feb 6, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  15. Jul 8, 2019

    Passed: Electrical - Permanent Power

    Need Elv.letter To Release Power

    Inspected by Matt Forsyth

  16. Jul 9, 2019

    Release to power company

    Elevation Letter Rec'd

    Inspected by Lh

  17. Sep 19, 2019

    Passed: Building - Final

    Issued As A Private Rd-lh

    Inspected by Matt Forsyth