Permit Details

Permit Search

Permit

New Residential Construction

306 SW WOODLEAF COURT LAKE CITY FL 32024

Permit #
000037255
Application #
39592
Status Completed
  1. Submitted Sep 26, 2018
  2. Issued Sep 26, 2018
  3. Expires Jul 27, 2019
  4. Completed Jan 30, 2019

Property

Parcel #
02438-135
Owner
Mf Butler Homes,llc
Acres
0.51
Subdivision
Emerald Cove
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1840.00
Total Area (Sqft)
2715.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0585

Status & Review History

No status updates yet.

Contractors

  • Mark Bauer

    License
    CBC1259633
    Title
    —
    Role
    —

    County License & State License Expired.

Inspections

  1. Oct 5, 2018

    Passed: Building - Footer

    Inspected by Tommy Matthews

  2. Oct 5, 2018

    Passed: Engineering - Setbacks

    Inspected by Tommy Matthews

  3. Oct 19, 2018

    Release to power company

    Inspected by Troy Crews

  4. Oct 22, 2018

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  5. Oct 22, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    100 Psi

    Inspected by Troy Crews

  6. Oct 23, 2018

    Passed: Building - Slab

    Contractor Uses Bait System Termite Treatment

    Inspected by Troy Crews

  7. Nov 19, 2018

    Passed: Building - Roof Decking

    Inspected by Tommy Matthews

  8. Nov 19, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Tommy Matthews

  9. Nov 30, 2018

    Failed: Building - Framing

    Missed All Thread Green Paint By Rear Door To Right

    Inspected by Troy Crews

  10. Nov 30, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  11. Nov 30, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  12. Nov 30, 2018

    Failed: Plumbing/Gas - Rough In

    Needs Pressure On Water Lines

    Inspected by Troy Crews

  13. Dec 7, 2018

    Passed: Building - Framing

    Inspected by Troy Crews

  14. Dec 7, 2018

    Passed: Building - Insulation

    Inspected by Troy Crews

  15. Dec 7, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  16. Jan 8, 2019

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  17. Jan 9, 2019

    Release to power company

    Inspected by Laurie Hodson

  18. Jan 9, 2019

    Septic Release Inspection

    Inspected by Health Dept

  19. Jan 28, 2019

    Passed: Building - Final

    Blower Door Test Recieved

    Inspected by Troy Crews