Permit Details

Permit Search

Permit

New Residential Construction

300 SW BEYOUND CT
LAKE CITY, FL 32024

Permit #
000037168
Application #
39450
Status Completed
  1. Submitted Aug 31, 2018
  2. Issued Aug 31, 2018
  3. Expires Nov 14, 2020
  4. Completed Jul 31, 2020

Property

Parcel #
03707-018
Owner
Wayne Clemons Jr
Acres
10.02
Subdivision
Great South Timber Unrec.
Zoning
AG-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0395C
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
2721.00
Total Area (Sqft)
3661.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0718

Status & Review History

No status updates yet.

Contractors

This is an owner-builder project.

  • Wayne Clemons Jr

    License
    OWNER
    Title
    —
    Role
    —

Inspections

  1. Sep 5, 2018

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Sep 5, 2018

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Sep 19, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  4. Sep 28, 2018

    Passed: Building - Slab

    Inspected by Tommy Matthews

  5. Oct 16, 2018

    Passed: Building - Lintel/Tie Beam

    Inspected by Troy Crews

  6. Oct 16, 2018

    Passed: Building - Masonry Wall Reinforcing

    Inspected by Troy Crews

  7. Nov 30, 2018

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  8. Jul 17, 2019

    Passed: Building - Framing

    Inspected by Matt Forsyth

  9. Aug 13, 2019

    Passed: Building - Lath/Stucco

    Inspected by Matt Forsyth

  10. Sep 12, 2019

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  11. Sep 16, 2019

    Passed: Electrical - Rough In

    Inspected by Matt Forsyth

  12. Sep 16, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Matt Forsyth

  13. Sep 24, 2019

    Passed: Building - Insulation

    Inspected by Matt Forsyth

  14. Jan 15, 2020

    Rescheduled 1/21/2020:Building - Final

    Inspected by Janice Williams

  15. Jan 21, 2020

    Septic Release Inspection

    Inspected by Health Dept

  16. Jan 21, 2020

    Passed: Electrical - Permanent Power

    Inspected by Matt Forsyth

  17. Jan 21, 2020

    Release to power company

    Inspected by Matt Forsyth

  18. May 18, 2020

    Passed: Building - Final

    Inspected by Matt Forsyth

  19. Jul 31, 2020

    Certificate-Release Certificate

    Released When The Assessments Were Paid.

    Inspected by Matt Forsyth