Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
Partial West And North Walls |
Troy Crews |
8/27/2018 |
Passed: Engineering - Setbacks |
Per Site Plan According To Builder |
Troy Crews |
8/27/2018 |
Passed: Electrical - Underground Rough-In |
|
Troy Crews |
9/7/2018 |
Passed: Plumbing/Gas - Underground Rough-In |
|
Troy Crews |
9/7/2018 |
Passed: Building - Monolithic Slab |
|
Troy Crews |
9/10/2018 |
Passed: Engineering - Setbacks |
|
Troy Crews |
9/10/2018 |
Passed: Building - Insulation |
|
Troy Crews |
11/7/2018 |
Passed: Electrical - Rough In |
|
Troy Crews |
11/7/2018 |
Rescheduled 11/9/2018:Mechanical - Rough In |
|
Troy Crews |
11/7/2018 |
Passed: Plumbing/Gas - Rough In |
|
Troy Crews |
11/7/2018 |
Rescheduled 11/8/2018:Building - Framing |
|
Troy Crews |
11/7/2018 |
Rescheduled 11/8/2018:Mechanical - Rough In |
|
Troy Crews |
11/7/2018 |
Passed: Building - Framing |
Interior Walls And Fire Barrier Wall |
Troy Crews |
11/8/2018 |
Failed: Mechanical - Rough In |
Bath Fans Not Complete |
Troy Crews |
11/8/2018 |
Rescheduled 11/14/2018:Mechanical - Rough In |
|
Troy Crews |
11/9/2018 |
Passed: Mechanical - Rough In |
|
Troy Crews |
11/14/2018 |
Passed: Electrical - Permanent Power |
Need Septic And Driveway Finals |
Troy Crews |
1/22/2019 |
Release to power company |
|
Laurie Hodson |
1/24/2019 |
Septic Release Inspection |
Drive Is Existing Per Application |
Health Dept |
1/24/2019 |
Failed: Building - Final |
Need Grab Rails ,gfci In Warehouse East Wall, 1fire Ext. |
Troy Crews |
2/1/2019 |
Failed: Building - Final |
Need Gfci On Three Plugs In Warehouse And Fire Extinguisher Also Grab Bars In Bathroom |
Troy Crews |
2/4/2019 |
Failed: Engineering - Zoning Final |
Site Work Is Not Complete. No Landscaping Has Been Placed. Landscaping Must Comply With The Approved Site Plan. Also, Erosion Into The Stormwater Management System Has Blocked Drains. Stormwater Management System And Drains Must Be Cleaned Out And Erosion Stabilization Must Be Utilized. |
Brandon Stubbs |
2/5/2019 |
Passed: Engineering - Zoning Final |
|
Brandon Stubbs |
2/19/2019 |
Failed: Building - Final |
Gfci Needed On East Wall Warehouse, Grab Bar Behind Toilet |
Troy Crews |
3/29/2019 |
Passed: Building - Final |
|
Troy Crews |
4/2/2019 |