Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Randy Jones |
7/10/2018 |
Passed: Engineering - Setbacks |
|
Randy Jones |
7/10/2018 |
Passed: Engineering - Initial Driveway |
|
Dm |
7/13/2018 |
Passed: Plumbing/Gas - Underground Rough-In |
|
Randy Jones |
7/27/2018 |
Passed: Building - Slab |
|
Troy Crews |
7/31/2018 |
Passed: Building - Monolithic Slab |
|
Troy Crews |
7/31/2018 |
Passed: Engineering - Setbacks |
|
Troy Crews |
7/31/2018 |
Release to power company |
|
Randy Jones |
8/1/2018 |
Passed: Electrical - Temporary Service |
|
Randy Jones |
8/2/2018 |
Failed: Building - Ext Strapping/Wall Sheathing |
Spacing Not Right |
Tommy Matthews |
10/2/2018 |
Passed: Building - Roof Decking |
Not Complete. Breezeway Not Built |
Tommy Matthews |
10/2/2018 |
Failed: Building - Framing |
Rear Porch And Carport Beams Not As Per Requirements.
breezeway Not Built.
porch Columns Not Installed.
trusses Do Not Match Plans. Need Layout To Verify. Need Approved Truss Details That Were Approved At Permitting Unless Changed And Then We Need New Approved Details. Check Uplift For Each Truss Throughout. Check Engineering Braces. T01 Seems To Be Missing One Brace.
stopped At This Point And Did Not Check Anchor Bolts Or Window And Door Headers. |
Tommy Matthews |
10/2/2018 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Tommy Matthews |
10/4/2018 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Tommy Matthews |
10/8/2018 |
Cancelled: Electrical - Rough In |
|
Troy Crews |
10/10/2018 |
Failed: Building - Framing |
Need Engineering For Truss Tie Downs Porch Beams And Mounting Of Porch Post |
Troy Crews |
10/12/2018 |
Passed: Electrical - Rough In |
|
Troy Crews |
10/12/2018 |
Rescheduled 10/22/2018:Building - Framing |
|
Troy Crews |
10/19/2018 |
Passed: Building - Framing |
|
Troy Crews |
10/22/2018 |
Passed: Building - Insulation |
|
Troy Crews |
11/5/2018 |
Rescheduled 11/7/2018:Mechanical - Above Ceiling |
|
Troy Crews |
11/5/2018 |
Passed: Mechanical - Above Ceiling |
|
Tommy Matthews |
11/7/2018 |
Failed: Electrical - Permanent Power |
House Needs To Be Lockable. |
Tommy Matthews |
1/15/2019 |
Septic Release Inspection |
|
Health Dept |
1/15/2019 |
Passed: Electrical - Permanent Power |
Pictures Sent, Need Final On Culvert 2633 |
Tommy Matthews |
1/18/2019 |
Release to power company |
|
Laurie Hodson |
2/4/2019 |
Rescheduled 4/8/2019:Building - Final |
|
Troy Crews |
4/5/2019 |
Passed: Building - Final |
Release Of Co Pending Blower Door Test |
Troy Crews |
4/8/2019 |