Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit
Address 215 SW BEACON WAY LAKE CITY FL 3205
Parcel #: 02951-113
Acres: 0.48
Owner: Eric & Rebecca Woods
Subdivision: Amelia Landing
Zoning: PRD
Flood Zone: X
District: 5
Application #: 38353
Permit #: 000036839
Related Permit:
Submitted: Monday, June 11, 2018
Issued: Monday, June 11, 2018
Expires: Monday, November 5, 2018
Completed: Monday, November 5, 2018
Status: Completed
Septic Release? No
Notes:
NOC ON FILE. MFE 116.50', ELEVATION LETTER REC'D AT 117.52' Blower door test recieved
Job Details
This is the construction of a SFD/UTILITY
Heated Area (Sqft) 1669.00
Total Area (Sqft) 2325.00
Stories 1
Setbacks Front 25.00
Setback Side 1 10.00
Setback Side 2 10.00
Setbacks Rear 15.00
Septic# CITY
Power Company CLAY
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Fema map number 12023C0293D
Review Notes
Contractors
Name/ Business License Title Role
Adam Papka

County License & State License & Liability Insurance & Workers Comp Expired.
CBC1253409
Inspections
Inspection Notes Performed By Date
Failed: Electrical - Temporary Service Ground Not Connected Troy Crews 6/14/2018
Passed: Plumbing/Gas - Underground Rough-In Troy Crews 6/14/2018
Passed: Building - Slab Troy Crews 6/18/2018
Failed: Electrical - Temporary Service No Ground Connected Troy Crews 6/18/2018
Release to power company Troy Crews 7/19/2018
Passed: Electrical - Temporary Service Troy Crews 7/20/2018
Failed: Building - Framing Need Tempered Glass Adjacent To Back Door Troy Crews 7/31/2018
Passed: Electrical - Rough In Troy Crews 7/31/2018
Passed: Mechanical - Rough In Troy Crews 7/31/2018
Passed: Plumbing/Gas - Rough In Troy Crews 7/31/2018
Passed: Building - Insulation Reschedule Framing When Window Is Change Troy Crews 8/6/2018
Passed: Electrical - Permanent Power City Utilities Tommy Matthews 10/19/2018
Release to power company Laurie Hodson 10/22/2018
Passed: Building - Final Release Pending Blower Test, Rec'd 11/2/18 Troy Crews 11/2/2018
Documents
File Name Date File Size
36839 Elevation Letter 2018-10-22 08.27.05.967.pdf 2023.12.26 188.66kB
Permit-000036839.pdf 2023.12.26 28.19kB