Permit Details

Permit Search

Permit

New Residential Construction

720 SW HAPPY JACK DR LAKE CITY FL 32024

Permit #
000036743
Application #
37932
Status Completed
  1. Submitted May 16, 2018
  2. Issued May 16, 2018
  3. Expires Apr 22, 2019
  4. Completed Oct 31, 2018

Property

Parcel #
00415-107
Owner
James & Kathryn Bower
Acres
10.00
Subdivision
Southwest Estates Unrec
Zoning
A-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0360C
This is the construction of a
SFD/UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
1725.00
Total Area (Sqft)
2589.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0304

Status & Review History

No status updates yet.

Contractors

  • Matthew Erkinger, Sr.

    License
    CRC1330825
    Title
    —
    Role
    —

    County License & State License & Liability Insurance Expired.

Inspections

  1. May 29, 2018

    Passed: Building - Footer

    Inspected by Troy Crews

  2. May 29, 2018

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Jun 13, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  4. Jun 15, 2018

    Passed: Building - Slab

    Inspected by Randy Jones

  5. Jul 25, 2018

    Passed: Building - Roof Decking

    Inspected by Tommy Matthews

  6. Jul 25, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Tommy Matthews

  7. Aug 6, 2018

    Passed: Building - Framing

    Inspected by Troy Crews

  8. Aug 6, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  9. Aug 6, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  10. Aug 6, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  11. Aug 10, 2018

    Passed: Building - Insulation

    Inspected by Troy Crews

  12. Sep 26, 2018

    Passed: Electrical - Permanent Power

    Inspected by Tommy Matthews

  13. Oct 4, 2018

    Release to power company

    Inspected by Laurie Hodson

  14. Oct 4, 2018

    Septic Release Inspection

    Inspected by Health Dept

  15. Oct 24, 2018

    Passed: Building - Final

    Release Of Co Pending Blower Door Test

    Inspected by Troy Crews