Inspection |
Notes |
Performed By |
Date |
Engineering-Initial Driveway |
|
David Mccormick |
4/30/2018 |
Passed: Building - Footer |
|
Randy Jones |
5/4/2018 |
Passed: Engineering - Setbacks |
|
Randy Jones |
5/4/2018 |
Failed: Building - Slab |
Need Letter From Plumber That Plumbing Is To Code Prior To Pour |
Troy Crews |
5/21/2018 |
Passed: Plumbing/Gas - Underground Rough-In |
Based On Letter From Plumber |
Troy Crews |
5/23/2018 |
Passed: Building - Slab |
|
Troy Crews |
5/23/2018 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
6/5/2018 |
Release to power company |
|
Troy Crews |
6/5/2018 |
Passed: Building - Roof Decking |
|
Troy Crews |
6/21/2018 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
6/21/2018 |
Failed: Building - Framing |
Check All Anchor Bolts For Tightness ,missing Bolt Right Side Doorway At Garage And Missing Washers |
Troy Crews |
7/5/2018 |
Passed: Electrical - Rough In |
|
Troy Crews |
7/5/2018 |
Passed: Mechanical - Rough In |
|
Troy Crews |
7/5/2018 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Troy Crews |
7/5/2018 |
Rescheduled 7/10/2018:Building - Insulation |
|
Troy Crews |
7/9/2018 |
Passed: Building - Insulation |
|
Troy Crews |
7/10/2018 |
Passed: Building - Framing |
Anchor Bolts Corrected |
Troy Crews |
7/10/2018 |
Release to power company |
|
Laurie Hodson |
9/7/2018 |
Passed: Engineering - Final Driveway |
|
David Mccormick |
9/7/2018 |
Septic Release Inspection |
Rec'd Driveway Final |
Health Dept |
9/7/2018 |
Passed: Electrical - Permanent Power |
Need Driveway Final |
Troy Crews |
9/7/2018 |
Failed: Building - Final |
Need Blower Door Test.
need Bumper Protection Foe Ac In Garage. |
Tommy Matthews |
9/26/2018 |
Passed: Building - Final |
|
Tommy Matthews |
10/1/2018 |