Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Dm |
3/9/2018 |
Passed: Building - Footer |
|
Troy Crews |
3/15/2018 |
Passed: Engineering - Setbacks |
|
Troy Crews |
3/15/2018 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
3/15/2018 |
Release to power company |
|
Troy Crews |
3/15/2018 |
Passed: Plumbing/Gas - Underground Rough-In |
|
Troy Crews |
3/26/2018 |
Passed: Building - Slab |
|
Troy Crews |
4/6/2018 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
4/6/2018 |
Passed: Building - Roof Decking |
|
Tommy Matthews |
5/1/2018 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Tommy Matthews |
5/1/2018 |
Failed: Building - Framing |
Need New Set Truss Plans Stamped Set Not Matching House, Check King Studs Large Openings, Bottom Plate Splice In Garage Needs Bolt, King Studs Needed On Garage Header |
Troy Crews |
5/9/2018 |
Failed: Building - Framing |
Items On Notes Not Corrected Do Not Insulate |
Troy Crews |
5/15/2018 |
Passed: Electrical - Rough In |
|
Troy Crews |
5/15/2018 |
Passed: Mechanical - Rough In |
|
Troy Crews |
5/15/2018 |
Passed: Plumbing/Gas - Rough In |
|
Troy Crews |
5/15/2018 |
Passed: Building - Framing |
Items Corrected |
Troy Crews |
5/16/2018 |
Cancelled: Electrical - Rough In |
|
Troy Crews |
5/16/2018 |
Cancelled: Mechanical - Rough In |
|
Troy Crews |
5/16/2018 |
Cancelled: Plumbing/Gas - Rough In |
|
Troy Crews |
5/16/2018 |
Passed: Building - Insulation |
|
Troy Crews |
5/18/2018 |
Passed: Engineering - Final Driveway |
|
David Mccormick |
7/25/2018 |
Septic Release Inspection |
|
Health Dept |
7/25/2018 |
Passed: Electrical - Permanent Power |
Rec'd All, Need Elevation Confirmation Also Door Locks |
Troy Crews |
8/7/2018 |
Release to power company |
|
Laurie Hodson |
8/10/2018 |
CERTIFICATE OF OCCUPANCY/COMPLETION DATE |
|
|
8/15/2018 |
Passed: Building - Final |
Blower Door Test Recieved |
Troy Crews |
8/15/2018 |