Permit Details

Permit Search

Permit

New Residential Construction

278 NE DERBY TERR LAKE CITY FL 32055

Permit #
000036395
Application #
36720
Status Completed
  1. Submitted Mar 1, 2018
  2. Issued Mar 1, 2018
  3. Expires Sep 28, 2019
  4. Completed Mar 6, 2018

Property

Parcel #
05731-000
Owner
Georgia Muldrow
Acres
0.20
Subdivision
Carolyn Heights
Zoning
RSF-MH-2
Flood zone
X
District
1

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0305D
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0160

Status & Review History

No status updates yet.

Contractors

  • Jacob Bouroage

    License
    CBC1255569
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Mar 1, 2018

    Septic Release Inspection

    Inspected by Health Dept

  2. Mar 6, 2018

    Failed: Engineering - Zoning Final

    Need Variance Or Move House Towards Rear Of Lot

    Inspected by Troy Crews

  3. Apr 3, 2018

    Cancelled: Building - Footer

    Inspected by Troy Crews

  4. Apr 3, 2018

    Passed: Engineering - Setbacks

    String Lines Meet Setbacks Will Re Check On Foundation Inspection

    Inspected by Troy Crews

  5. Apr 5, 2018

    Passed: Building - Footer

    Inspected by Troy Crews

  6. Apr 5, 2018

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  7. Apr 24, 2018

    Release to power company

    Inspected by Randy Jones

  8. Apr 25, 2018

    Passed: Electrical - Temporary Service

    Inspected by Randy Jones

  9. Apr 27, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  10. May 8, 2018

    Release to power company

    Account Number 1272278100

    Inspected by Randy Jones

  11. May 9, 2018

    Passed: Building - Slab

    Inspected by Troy Crews

  12. Jun 5, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  13. Jun 5, 2018

    Passed: Building - Framing

    Inspected by Troy Crews

  14. Jun 15, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  15. Jun 15, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  16. Jun 15, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  17. Jul 9, 2018

    Passed: Building - Insulation

    Inspected by Troy Crews

  18. Sep 13, 2018

    Passed: Electrical - Permanent Power

    Existing Drive

    Inspected by Troy Crews

  19. Sep 13, 2018

    Release to power company

    Inspected by Troy Crews

  20. Oct 23, 2018

    Passed: Building - Final

    Release Of Co Pending Back Step And Blower Door, 11/6/18-rec'd Bdt Results

    Inspected by Troy Crews

  21. Apr 1, 2019

    Passed: Building - Final

    Inspected by Troy Crews