Status Completed
  1. Submitted Feb 7, 2018
  2. Issued Nov 12, 2019
  3. Expires Nov 28, 2021
  4. Completed Jan 18, 2023

Property

Parcel #
09369-000
Owner
Olivia Rae Farms Inc
Acres
112.00
Subdivision
—
Zoning
AG-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0415C
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
3632.00
Total Area (Sqft)
5719.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Septic# (00-0000) or (X00-000)
16-0557-N

Status & Review History

  1. Permit Renewed

Contractors

  • Lewis Walker

    License
    OWNER
    Title
    —
    Role
    —

Inspections

  1. Jan 10, 2020

    Rescheduled 1/13/2020:Building - Footer

    Inspected by Janice Williams

  2. Jan 13, 2020

    Passed: Building - Footer

    Inspected by Troy Crews

  3. Jan 31, 2020

    Passed: Building - Footer

    Interior Pads And Porch Pads

    Inspected by Troy Crews

  4. Jan 31, 2020

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Feb 14, 2020

    Cancelled: Building - Footer

    Inspected by Troy Crews

  6. Feb 14, 2020

    Cancelled: Engineering - Setbacks

    Inspected by Troy Crews

  7. Feb 14, 2020

    Passed: Building - Lintel/Tie Beam

    Block Cells For Stemwall And Piers For Porches

    Inspected by Troy Crews

  8. Jul 15, 2020

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  9. Jul 15, 2020

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  10. Jul 15, 2020

    Failed: Building - Framing

    Add Nails And Straps To Double Girder Trusses Call Framing Back In With Rough Mechanicals

    Inspected by Troy Crews

  11. Aug 13, 2020

    Cancelled: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  12. Aug 13, 2020

    Cancelled: Building - Lintel/Tie Beam

    Inspected by Troy Crews

  13. Aug 13, 2020

    Cancelled: Building - Roof Decking

    Inspected by Troy Crews

  14. Aug 13, 2020

    Cancelled: Building - Strapping

    Inspected by Troy Crews

  15. Aug 13, 2020

    Cancelled: Building - Wall Sheathing

    Inspected by Troy Crews

  16. Aug 14, 2020

    Passed: Building - Framing

    Times Corrected

    Inspected by Troy Crews

  17. Aug 14, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  18. Aug 14, 2020

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  19. Aug 14, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  20. Aug 14, 2020

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Troy Crews

  21. Aug 25, 2020

    Passed: Building - Insulation

    Inspected by Troy Crews

  22. Jun 1, 2021

    Passed: Building - Final

    Inspected by Troy Crews