Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Troy Crews |
2/1/2018 |
Passed: Engineering - Setbacks |
|
Troy Crews |
2/1/2018 |
Failed: Plumbing/Gas - Underground Rough-In |
|
Tommy Matthews |
2/12/2018 |
Passed: Plumbing/Gas - Underground Rough-In |
|
Tommy Matthews |
2/13/2018 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
2/19/2018 |
Release to power company |
|
Troy Crews |
2/19/2018 |
Passed: Building - Slab |
|
Tommy Matthews |
2/26/2018 |
Passed: Building - Roof Decking |
|
Tommy Matthews |
3/9/2018 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Tommy Matthews |
3/9/2018 |
Passed: Electrical - Rough In |
|
Tommy Matthews |
3/29/2018 |
Passed: Mechanical - Rough In |
|
Tommy Matthews |
3/29/2018 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Tommy Matthews |
3/29/2018 |
Passed: Plumbing/Gas - Water Pipe |
|
Tommy Matthews |
3/29/2018 |
Passed: Plumbing/Gas - Rough In |
|
Tommy Matthews |
3/29/2018 |
Passed: Building - Framing |
|
Tommy Matthews |
3/29/2018 |
Passed: Building - Insulation |
|
Tommy Matthews |
4/30/2018 |
Rescheduled 10/12/2018:Electrical - Permanent Power |
Office Closed Due To Hurricane Michael |
Laurie Hodson |
10/9/2018 |
Rescheduled 10/10/2018:Electrical - Permanent Power |
|
Troy Crews |
10/10/2018 |
Rescheduled 10/11/2018:Electrical - Permanent Power |
|
Troy Crews |
10/10/2018 |
Failed: Electrical - Permanent Power |
House Must Be Lockable Including Garage Door.
need Septic Tank Final, Rec'd Septic On 10/15/18 |
Tommy Matthews |
10/11/2018 |
Septic Release Inspection |
|
Health Dept |
10/15/2018 |
Passed: Electrical - Permanent Power |
|
Tommy Matthews |
10/16/2018 |
Release to power company |
|
Tommy Matthews |
10/16/2018 |
Cancelled: Re-Roof - Final |
|
Troy Crews |
12/7/2018 |
Passed: Building - Final |
|
Troy Crews |
12/7/2018 |