Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 199 SW CAMPHOR COURT LAKE CITY FL 32024
Parcel #: 02732-312
Acres: 0.50
Owner: Gibraltar Contracting,llc
Subdivision: Laurel Lake
Zoning: RSF-2
Flood Zone: X
District:
Application #: 36485
Permit #: 000036242
Related Permit: Culvert Waiver: 000002527
Submitted: Wednesday, January 24, 2018
Issued: Wednesday, January 24, 2018
Expires: Friday, June 29, 2018
Completed: Friday, June 29, 2018
Status: Completed
Septic Release? Yes
Notes:
NOC ON FILE. MFE @ 114.00. ELEVATION CONFIRMATION LETTER @ SLAB. Blower door test recieved
Job Details
Elevation regulation Accessory Use
Finished floor requirement EXISTING BUILDING Non-Habitable Structure
Fema map number 12023C0485C
What is the power service for? Garage
Other job details: EXISTING
Power Company Clay Electric
Septic # (00-0000) or (X00-000) X20-091
Electrical Code Edition 2014 National Electrical Code
Meter or Account: Account
Number of requested AMPS for electrical service: 200
Is the power service? New
Residential or Commercial? Residential
Review Notes
Contractors
Name/ Business License Title Role
Mark Bauer

Employees Workers Comp Expired.
CBC1259633
Inspections
Inspection Notes Performed By Date
Failed: Building - Footer Randy Jones 1/29/2018
Failed: Engineering - Setbacks Randy Jones 1/29/2018
Passed: Building - Footer Troy Crews 1/30/2018
Passed: Engineering - Setbacks Troy Crews 1/30/2018
Failed: Electrical - Temporary Service Not Installed Troy Crews 2/2/2018
Passed: Electrical - Temporary Service Troy Crews 2/5/2018
Release to power company Troy Crews 2/5/2018
Passed: Plumbing/Gas - Underground Rough-In Troy Crews 2/16/2018
Passed: Building - Slab Contractor Uses Termite Bait System Troy Crews 2/20/2018
Failed: Building - Roof Decking Not Finished Tommy Matthews 4/3/2018
Passed: Building - Ext Strapping/Wall Sheathing Strapping Not Installed. Look For On Next Inspection Tommy Matthews 4/3/2018
Passed: Building - Ext Strapping/Wall Sheathing Troy Crews 4/12/2018
Cancelled: Building - Ext Strapping/Wall Sheathing Troy Crews 4/16/2018
Failed: Building - Framing Check Truss Engineering, Back Porch Post Missing, Check All Headers To Match Plans Jack And King Studs Etc. Troy Crews 4/16/2018
Passed: Electrical - Rough In Troy Crews 4/16/2018
Passed: Mechanical - Rough In Troy Crews 4/16/2018
Passed: Plumbing/Gas - Rough In Troy Crews 4/16/2018
Passed: Building - Framing Troy Crews 4/17/2018
Passed: Building - Insulation Troy Crews 4/19/2018
Passed: Electrical - Permanent Power Need Health Release Troy Crews 6/7/2018
Release to power company City Sewer Laurie Hodson 6/18/2018
CERTIFICATE OF OCCUPANCY/COMPLETION DATE 6/28/2018
Passed: Building - Final Release Of C.o. Pending Blower Door Test, Rec'd 6/28/18 Troy Crews 6/28/2018
Documents
File Name Date File Size