Inspection |
Notes |
Performed By |
Date |
Failed: Building - Footer |
|
Randy Jones |
1/29/2018 |
Failed: Engineering - Setbacks |
|
Randy Jones |
1/29/2018 |
Passed: Building - Footer |
|
Troy Crews |
1/30/2018 |
Passed: Engineering - Setbacks |
|
Troy Crews |
1/30/2018 |
Failed: Electrical - Temporary Service |
Not Installed |
Troy Crews |
2/2/2018 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
2/5/2018 |
Release to power company |
|
Troy Crews |
2/5/2018 |
Passed: Plumbing/Gas - Underground Rough-In |
|
Troy Crews |
2/16/2018 |
Passed: Building - Slab |
Contractor Uses Termite Bait System |
Troy Crews |
2/20/2018 |
Failed: Building - Roof Decking |
Not Finished |
Tommy Matthews |
4/3/2018 |
Passed: Building - Ext Strapping/Wall Sheathing |
Strapping Not Installed. Look For On Next Inspection |
Tommy Matthews |
4/3/2018 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
4/12/2018 |
Cancelled: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
4/16/2018 |
Failed: Building - Framing |
Check Truss Engineering, Back Porch Post Missing, Check All Headers To Match Plans Jack And King Studs Etc. |
Troy Crews |
4/16/2018 |
Passed: Electrical - Rough In |
|
Troy Crews |
4/16/2018 |
Passed: Mechanical - Rough In |
|
Troy Crews |
4/16/2018 |
Passed: Plumbing/Gas - Rough In |
|
Troy Crews |
4/16/2018 |
Passed: Building - Framing |
|
Troy Crews |
4/17/2018 |
Passed: Building - Insulation |
|
Troy Crews |
4/19/2018 |
Passed: Electrical - Permanent Power |
Need Health Release |
Troy Crews |
6/7/2018 |
Release to power company |
City Sewer |
Laurie Hodson |
6/18/2018 |
CERTIFICATE OF OCCUPANCY/COMPLETION DATE |
|
|
6/28/2018 |
Passed: Building - Final |
Release Of C.o. Pending Blower Door Test, Rec'd 6/28/18 |
Troy Crews |
6/28/2018 |