Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 336 SW MAYFAIR LN LAKE CITY FL 32024
Parcel #: 02911-351
Acres: 0.81
Owner: Trent Giebeig Construction,llc
Subdivision: May-fair
Zoning: RSF-2
Flood Zone: X
District: 3
Application #: 36469
Permit #: 000036231
Related Permit: Culvert: 000002523
Submitted: Monday, January 22, 2018
Issued: Monday, January 22, 2018
Expires: Wednesday, May 23, 2018
Completed: Wednesday, May 23, 2018
Status: Completed
Septic Release? Yes
Notes:
MFE @ 158.00'.ELEVATION CERTIFICATION PRESENT @ SLAB. ELEVATION LETTER REC'D AT 156.84'
Job Details
Finished floor requirement
Fema map number 12023C0167D
Standards Culvert installation shall conform to the approved site plan standards
Review Notes
Contractors
Name/ Business License Title Role
B. Trent Giebeig

CRC1330693
Inspections
Inspection Notes Performed By Date
Passed: Engineering - Initial Driveway Dm 1/31/2018
Electrical -Temporary Service Troy Crews 2/1/2018
Release to power company Troy Crews 2/1/2018
Passed: Building - Footer Troy Crews 2/1/2018
Passed: Engineering - Setbacks Troy Crews 2/1/2018
Rescheduled 2/1/2018:Electrical - Temporary Service Troy Crews 2/1/2018
Passed: Electrical - Temporary Service Troy Crews 2/1/2018
Passed: Plumbing/Gas - Rough In Troy Crews 2/7/2018
Passed: Building - Slab Troy Crews 2/9/2018
Failed: Building - Ext Strapping/Wall Sheathing Not Ready. Needs To Be Nailed Off. Tommy Matthews 3/23/2018
Passed: Building - Roof Decking Troy Crews 3/23/2018
Passed: Building - Ext Strapping/Wall Sheathing Troy Crews 3/23/2018
Passed: Building - Framing Troy Crews 4/2/2018
Passed: Electrical - Rough In Troy Crews 4/2/2018
Passed: Mechanical - Rough In Troy Crews 4/2/2018
Passed: Plumbing/Gas - Rough In Troy Crews 4/2/2018
Cancelled: Mechanical - Pipe Pressure Test Troy Crews 4/2/2018
Passed: Plumbing/Gas - Tub Set/Shower Pan Troy Crews 4/2/2018
Passed: Plumbing/Gas - Water Pipe Troy Crews 4/2/2018
Passed: Building - Insulation Tommy Matthews 4/4/2018
Passed: Electrical - Permanent Power Tommy Matthews 5/8/2018
Passed: Engineering - Final Driveway Dm 5/10/2018
Septic Release Inspection Health Dept 5/10/2018
Release to power company Laurie Hodson 5/14/2018
CERTIFICATE OF OCCUPANCY/COMPLETION DATE 5/23/2018
Passed: Building - Final Troy Crews 5/23/2018