Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Troy Crews |
2/15/2018 |
Passed: Engineering - Setbacks |
|
Troy Crews |
2/15/2018 |
Passed: Plumbing/Gas - Rough In |
|
Tommy Matthews |
4/3/2018 |
Passed: Building - Slab |
|
Troy Crews |
4/10/2018 |
Passed: Building - Lintel/Tie Beam |
|
Troy Crews |
5/2/2018 |
Passed: Building - Roof Decking |
Partial. Exclude Front Porch,rear Portion At Top Near Peak |
Tommy Matthews |
5/18/2018 |
Passed: Building - Roof Decking |
|
Troy Crews |
5/23/2018 |
Release to power company |
Corrected Power Company |
Laurie Hodson |
7/18/2018 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
7/18/2018 |
Release to power company |
|
Troy Crews |
7/18/2018 |
Failed: Building - Framing |
Need To Strap Trusses T-24 T-25 And T-26 At Interior Wall Bearing Point |
Troy Crews |
10/15/2018 |
Passed: Electrical - Rough In |
|
Troy Crews |
10/15/2018 |
Passed: Mechanical - Rough In |
|
Troy Crews |
10/15/2018 |
Failed: Plumbing/Gas - Rough In |
P-trap Washing Machine Line ? |
Troy Crews |
10/15/2018 |
Cancelled: Mechanical - Rough In |
|
Troy Crews |
10/18/2018 |
Failed: Plumbing/Gas - Rough In |
P-trap Washing Machine Drain ? |
Troy Crews |
10/18/2018 |
Passed: Building - Framing |
Straps Installed |
Troy Crews |
10/19/2018 |
Passed: Plumbing/Gas - Rough In |
P Trap Under Slab For Washer Per Plumber |
Troy Crews |
10/24/2018 |
Electrical -Permanent Power |
|
Troy Crews |
10/31/2019 |
Release to power company |
|
Troy Crews |
10/31/2019 |
Release to power company |
|
|
2/19/2020 |
Release to power company |
Resent To Power Company |
Laurie Hodson |
7/7/2020 |
Failed: Building - Final |
Need Tie Down Clips On Air Condenser Unit, Blower Door Test, Final Termite Treatment, Remove Limb For Access To Garage. |
Troy Crews |
4/23/2021 |
Passed: Building - Final |
Blower Door Received, Termite Sticker On Panel. Items Corrected |
Troy Crews |
4/30/2021 |