Inspection |
Notes |
Performed By |
Date |
Temporary Power Inspection |
|
Troy Crews |
10/25/2017 |
Foundation Inspection |
|
Troy Crews |
10/25/2017 |
Setback Inspection |
|
Troy Crews |
10/25/2017 |
Passed: Engineering - Initial Driveway |
|
Dm |
10/30/2017 |
Underslab Rough Plumbing Inspection |
|
Troy Crews |
11/1/2017 |
Slab Inspection |
|
Troy Crews |
11/13/2017 |
Sheathing and Nailing Inspection |
|
Troy Crews |
11/27/2017 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
11/27/2017 |
Passed: Building - Ext. Dry In/In Progress |
|
Troy Crews |
11/27/2017 |
Rough-In Plumbing Inspection |
|
Troy Crews |
12/13/2017 |
Electrical Rough-In Inspection |
|
Troy Crews |
12/13/2017 |
Heat and Air Duct Inspection |
|
Troy Crews |
12/13/2017 |
Passed: Building - Ext. Dry In/In Progress |
|
Troy Crews |
12/13/2017 |
Passed: Electrical - Rough In |
|
Troy Crews |
12/13/2017 |
Passed: Mechanical - Rough In |
|
Troy Crews |
12/13/2017 |
Passed: Plumbing/Gas - Sanitary |
|
Troy Crews |
12/13/2017 |
Passed: Plumbing/Gas - Water Pipe |
|
Troy Crews |
12/13/2017 |
Failed: Building - Framing |
Anchor Bolts , Front Porch Rafter And Ledger Attachment |
Troy Crews |
12/13/2017 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Troy Crews |
12/13/2017 |
Framing Inspection |
|
|
12/20/2017 |
Insulation Inspection |
|
Troy Crews |
12/20/2017 |
Passed: Building - Framing |
|
Troy Crews |
12/20/2017 |
Passed: Building - Insulation |
|
Troy Crews |
12/20/2017 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
2/19/2018 |
Passed: Plumbing/Gas - Sanitary |
|
Troy Crews |
2/19/2018 |
Septic Release Inspection |
|
Health Dept |
2/21/2018 |
Passed: Engineering - Final Driveway |
|
Dm |
2/23/2018 |
Release to power company |
|
Dm |
2/23/2018 |
Passed: Engineering - Final Driveway |
|
Dm |
2/23/2018 |
Final Inspection |
|
|
3/16/2018 |
Passed: Building - Final |
Blower Door Test In Documents |
Troy Crews |
3/16/2018 |
CERTIFICATE OF OCCUPANCY/COMPLETION DATE |
|
|
3/19/2018 |