Permit Details

Permit Search

Permit

New Residential Construction

269 SW BIRCH GLN
LAKE CITY, FL 32024

Permit #
000035843
Application #
35856
Status Completed
  1. Submitted Oct 3, 2017
  2. Issued Oct 3, 2017
  3. Expires Sep 18, 2018
  4. Completed Mar 23, 2018

Property

Parcel #
02732-207
Owner
Millenia Capital, Inc.
Acres
0.58
Subdivision
Laurel Lake
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1763.00
Total Area (Sqft)
2470.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
xCITY

Status & Review History

No status updates yet.

Contractors

  • Mark Bauer

    License
    CBC1259633
    Title
    —
    Role
    —

    County License & State License Expired.

Inspections

  1. Oct 6, 2017

    Foundation Inspection

    Inspected by Tommy Matthews

  2. Oct 6, 2017

    Setback Inspection

    Inspected by Tommy Matthews

  3. Oct 18, 2017

    Underslab Rough Plumbing Inspection

    Inspected by Tommy Matthews

  4. Oct 24, 2017

    Temporary Power Inspection

    Inspected by Troy Crews

  5. Oct 24, 2017

    Slab Inspection

    Inspected by Troy Crews

  6. Nov 22, 2017

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Tommy Matthews

  7. Nov 22, 2017

    Failed: Building - Framing

  8. Dec 8, 2017

    Rough-In Plumbing Inspection

    Inspected by Troy Crews

  9. Dec 8, 2017

    Electrical Rough-In Inspection

    Inspected by Troy Crews

  10. Dec 8, 2017

    Heat and Air Duct Inspection

    Inspected by Troy Crews

  11. Dec 8, 2017

    Failed: Building - Framing

    Add Clips To Inside Wall C-9 And C-13

    Inspected by Troy Crews

  12. Dec 8, 2017

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  13. Dec 8, 2017

    Passed: Plumbing/Gas - Sanitary

    Inspected by Troy Crews

  14. Dec 8, 2017

    Passed: Plumbing/Gas - Water Pipe

    Inspected by Troy Crews

  15. Dec 8, 2017

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  16. Dec 13, 2017

    Framing Inspection

    Inspected by Troy Crews

  17. Dec 13, 2017

    Passed: Building - Framing

    Clips Added

    Inspected by Troy Crews

  18. Dec 13, 2017

    Failed: Building - Insulation

    Not Done

    Inspected by Troy Crews

  19. Dec 15, 2017

    Insulation Inspection

    Inspected by Troy Crews

  20. Dec 15, 2017

    Passed: Building - Insulation

    Inspected by Troy Crews

  21. Mar 8, 2018

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  22. Mar 13, 2018

    Release to power company

    Inspected by Laurie Hodson

  23. Mar 22, 2018

    Passed: Building - Final

    Inspected by Troy Crews

  24. Mar 23, 2018

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE

  25. Requested

    Temp Power

    Awaiting inspection

  26. Requested

    Slab

    Awaiting inspection

  27. Requested

    Slab

    Awaiting inspection