Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Commercial Construction Permit
Address 13700 S US HIGHWAY 441 LAKE CITY FL 32025
Parcel #: 09563-001
Acres: 17.83
Owner: Love's Travel Stops & Country Stores Inc
Subdivision:
Zoning: CHI
Flood Zone: X
District: 4
Application #: 35844
Permit #: 000035832
Related Permit:
Submitted: Monday, October 2, 2017
Issued: Monday, October 2, 2017
Expires: Thursday, June 28, 2018
Completed: Thursday, June 28, 2018
Status: Completed
Septic Release? No
Notes:
SE 0569 APPR 2-23-17, MINIMUM FLOOR ELEVATION SET PER SITE PLAN AT 72' NOC, ELEVATION LETTER REC'D @ 72.02', ALL SIGNAGE INCLUDED, DOT PERMIT REC'D. PARTIAL FOUND.10.18.17-TC UNDER SLAB ELEC.10.25.17-TC,PLUMBING12.28.17
Job Details
This is the construction of a: LOVE'S TRAVEL STORE
Heated Area (Sqft) 11460.00
Total Area (Sqft) 33001.00
Total Estimated Cost 6900000.00
Stories 1
Setbacks Front 20.00
Setback Side 1 5.00
Setback Side 2 5.00
Setback Rear 15.00
Septic# COUNTY
Power Company CLAY
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Fema map number 12023C0415C
Review Notes
Contractors
Name/ Business License Title Role
Carl Herndon

County License & State License & Liability Insurance & Workers Comp Expired.
CBC047843
Inspections
Inspection Notes Performed By Date
Foundation Inspection Troy Crews 10/12/2017
Setback Inspection Troy Crews 10/12/2017
Temporary Power Inspection Troy Crews 10/13/2017
Passed: Foundation Troy Crews 10/25/2017
Slab Inspection Troy Crews 11/1/2017
Passed: Building - Footer Tire Shop Partial Troy Crews 12/6/2017
Cancelled: Building - Footer Troy Crews 12/6/2017
Rough-In Plumbing Inspection Troy Crews 12/12/2017
Passed: Plumbing/Gas - Underground Rough-In Waste Lines Tire Shop Troy Crews 12/12/2017
Monolithic Slab Inspection Troy Crews 12/13/2017
Passed: Building - Footer Partial Tire Shop Troy Crews 12/13/2017
Passed: Building - Slab Partial Slab Tire Store. Troy Crews 12/13/2017
Passed: Fire - Underground Main - Visual Done By F.d 12-13-17 Partial J.w. 12/13/2017
Passed: Building - Ext Strapping/Wall Sheathing Main Building Walls Troy Crews 12/14/2017
Underslab Rough Plumbing Inspection Troy Crews 12/18/2017
Passed: Plumbing/Gas - Underground Rough-In Troy Crews 12/18/2017
Passed: Fire - Underground Main - Visual Josh Wehinger 12/20/2017
Passed: Building - Slab Troy Crews 12/20/2017
Passed: Plumbing/Gas - Interceptor Grease Trap Troy Crews 12/20/2017
Framing Inspection Troy Crews 12/28/2017
Electrical Rough-In Inspection Troy Crews 12/28/2017
Passed: Building - Framing North End Bathroom Area Troy Crews 12/28/2017
Passed: Electrical - Rough In North End Bathroom Area Troy Crews 12/28/2017
Passed: Plumbing/Gas - Water Pipe North End Bathroom Area Troy Crews 12/28/2017
Passed: Fire - Underground Main - Visual Josh Wehinger 1/2/2018
Passed: Fire - Underground Main - Visual Done By Josh 1-2-18 Troy Crews 1/3/2018
Passed: Building - Insulation Exterior Walls North End Troy Crews 1/8/2018
Passed: Building - Insulation North End Exterior Walls Troy Crews 1/8/2018
Passed: Fire - Underground Main - Visual Josh Wehinger 1/11/2018
Passed: Building - Insulation South End Of Building Troy Crews 1/24/2018
Passed: Electrical - Rough In South End Of Building Troy Crews 1/24/2018
Passed: Plumbing/Gas - Rough In South End Of Building Troy Crews 1/24/2018
Passed: Building - Slab Truck Pump Area Troy Crews 2/5/2018
Passed: Building - Framing Framing And Wall Sheathing Need To Look At Roof Screws, Troy Crews 2/20/2018
Passed: Building - Insulation Troy Crews 3/5/2018
Passed: Building - Rated Assembly Fastening Troy Crews 3/5/2018
Passed: Building - Insulation Troy Crews 3/6/2018
Passed: Electrical - Rough In Troy Crews 3/6/2018
Passed: Plumbing/Gas - Rough In Troy Crews 3/6/2018
Rescheduled 3/9/2018:Building - Footer Will @ 601-470-8201 Laurie Hodson 3/8/2018
Rescheduled 3/9/2018:Engineering - Setbacks Laurie Hodson 3/8/2018
Passed: Building - Insulation Troy Crews 3/8/2018
Cancelled: Building - Footer Canceled By Will 601-470-8201 Laurie Hodson 3/9/2018
Rescheduled 3/14/2018:Building - Footer Will Changed Date (around Noon) Laurie Hodson 3/13/2018
Rescheduled 3/14/2018:Engineering - Setbacks Will Changed Date (around Noon) Laurie Hodson 3/13/2018
Cancelled: Building - Footer Troy Crews 3/14/2018
Passed: Mechanical - Kitchen Hood Grease Hoods Troy Crews 3/15/2018
Passed: Mechanical - Light Test Showed No Leaks Troy Crews 3/15/2018
Passed: Mechanical - Rough In Ceiling Rough In Troy Crews 3/16/2018
Rescheduled 3/20/2018:Building - Footer Troy Crews 3/19/2018
Rescheduled 3/20/2018:Engineering - Setbacks Troy Crews 3/19/2018
Passed: Building - Footer Mono Pole Sign Troy Crews 3/20/2018
Passed: Engineering - Setbacks Mono Pole Sign Troy Crews 3/20/2018
Passed: Building - Footer Troy Crews 3/27/2018
Passed: Engineering - Setbacks Troy Crews 3/27/2018
Passed: Building - Footer Troy Crews 4/13/2018
Passed: Engineering - Setbacks Troy Crews 4/13/2018
Passed: Electrical - Permanent Power Awaiting Release From Public Works On Water And Sewer Troy Crews 4/16/2018
Release to power company Letter From County Water System Rec'd Laurie Hodson 4/20/2018
Passed: Building - Above Ceiling Troy Crews 4/30/2018
Passed: Fire - Operational Test - Chemical/Gaseous Agent Josh Wehinger 5/18/2018
Passed: Building - Final Pending D.o.t. Final And Public Works Release Troy Crews 5/21/2018
Passed: Mechanical - Refrigeration Troy Crews 5/21/2018
Rescheduled 5/23/2018:Engineering - Zoning Final Troy Crews 5/21/2018
Passed: Fire - Fire Final Josh Wehinger 5/22/2018
Failed: Engineering - Zoning Final Site Was Not Complete. Landscaping Inspection Complete Brandon Stubbs 5/23/2018
Plumbing/Gas-Water Pipe Water & Sewer Services At County Connection Points Robert Dominque 5/25/2018
Passed: Engineering - Final Driveway Fdot Final Approval Rec'd Troy Register, Dot 6/4/2018
Passed: Engineering - Zoning Final All Complete Brandon Stubbs 6/5/2018
CERTIFICATE OF OCCUPANCY/COMPLETION DATE Temporary Co For Store Use 6/6/2018
Passed: Fire - Operational Test - Fire Pump Tire Store Josh Wehinger 6/6/2018
Release to power company Troy Crews 6/15/2018
Passed: Electrical - Permanent Power 100 Amp Three Phase For Fire Pump Troy Crews 6/18/2018
Building-Final All Completed Troy Crews 6/28/2018
Final Inspection Troy Crews 6/28/2018
CERTIFICATE OF OCCUPANCY/COMPLETION DATE 6/28/2018
Passed: Fire - Fire Final Josh Wehinger 6/28/2018
Passed: Fire - Operational Test - Fire Pump Troy Crews 6/28/2018
Passed: Fire - Fire Final Troy Crews 6/28/2018