Permit Details

Permit Search

Permit

New Residential Construction

323 SW LOGSTON CT FORT WHITE FL 32038

Permit #
000035796
Application #
35795
Status Completed
  1. Submitted Sep 19, 2017
  2. Issued Sep 19, 2017
  3. Expires Oct 22, 2018
  4. Completed Apr 25, 2018

Property

Parcel #
03767-107
Owner
Robert & Barbara March
Acres
5.01
Subdivision
Sedgefield S/d
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0480C
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
2001.00
Total Area (Sqft)
2763.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
17-0578

Status & Review History

No status updates yet.

Contractors

  • Robert March

    License
    OWNER
    Title
    —
    Role
    —

Inspections

  1. Sep 25, 2017

    Temporary Power Inspection

    Inspected by Troy Crews

  2. Sep 25, 2017

    Foundation Inspection

    Inspected by Troy Crews

  3. Sep 25, 2017

    Setback Inspection

    Inspected by Troy Crews

  4. Oct 11, 2017

    Underslab Rough Plumbing Inspection

    Inspected by Tommy Matthews

  5. Oct 16, 2017

    Slab Inspection

    Inspected by Tommy Matthews

  6. Dec 8, 2017

    Framing Inspection

    Inspected by Troy Crews

  7. Dec 8, 2017

    Heat and Air Duct Inspection

    Inspected by Troy Crews

  8. Dec 8, 2017

    Sheathing and Nailing Inspection

    Inspected by Troy Crews

  9. Dec 8, 2017

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  10. Dec 8, 2017

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  11. Dec 8, 2017

    Passed: Building - Framing

    Inspected by Troy Crews

  12. Dec 8, 2017

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  13. Dec 21, 2017

    Rough-In Plumbing Inspection

    Inspected by Tommy Matthews

  14. Dec 21, 2017

    Electrical Rough-In Inspection

    Inspected by Tommy Matthews

  15. Dec 21, 2017

    Passed: Electrical - Rough In

    Inspected by Tommy Matthews

  16. Dec 21, 2017

    Passed: Electrical - Above Ceiling

    Inspected by Tommy Matthews

  17. Dec 21, 2017

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Tommy Matthews

  18. Jan 4, 2018

    Passed: Building - Insulation

    Inspected by Tommy Matthews

  19. Jan 10, 2018

    Septic Release Inspection

    Inspected by Health Dept

  20. Apr 11, 2018

    Passed: Electrical - Permanent Power

    Inspected by Tommy Matthews

  21. Apr 11, 2018

    Release to power company

    Inspected by Tommy Matthews

  22. Apr 20, 2018

    Failed: Building - Final

    Need Final Termite Spray

    Inspected by Tommy Matthews

  23. Apr 25, 2018

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE

  24. Apr 25, 2018

    Passed: Building - Final

    Inspected by Tommy Matthews

  25. Apr 26, 2018

    Final Inspection

    Inspected by Tommy Matthews

  26. Requested

    Temp Power - Above ground

    Awaiting inspection

  27. Requested

    Foundation - Partial

    Awaiting inspection

  28. Requested

    Slab

    Awaiting inspection