Permit Details

Permit Search

Permit

New Residential Construction

170 SW HOLLY GLEN LAKE CITY FL 32024

Permit #
000035152
Application #
25507
Status Completed
  1. Submitted Apr 7, 2017
  2. Issued Apr 7, 2017
  3. Expires Oct 4, 2017
  4. Completed Aug 14, 2017

Property

Parcel #
03390-022
Owner
Lacey Developments Llc
Acres
1.35
Subdivision
—
Zoning
AG-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0383D
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
2023.00
Total Area (Sqft)
2791.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Septic# (00-0000) or (X00-000)
17-0215

Status & Review History

No status updates yet.

Contractors

  • Adam Papka

    Adam's Construction Llc

    License
    CBC1253409
    Title
    Building Contractor
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Apr 12, 2017

    Underslab Rough Plumbing Inspection

    Inspected by Randy Jones

  2. Apr 12, 2017

    Underslab Rough Plumbing Inspection

    Inspected by Randy Jones

  3. Apr 13, 2017

    Monolithic Slab Inspection

    Inspected by Randy Jones

  4. Apr 13, 2017

    Setback Inspection

    Inspected by Randy Jones

  5. Apr 13, 2017

    Monolithic Slab Inspection

    Inspected by Randy Jones

  6. Apr 13, 2017

    Setback Inspection

    Inspected by Randy Jones

  7. Apr 19, 2017

    Temporary Power Inspection

    Inspected by Randy Jones

  8. Apr 19, 2017

    Temporary Power Inspection

    Inspected by Randy Jones

  9. May 3, 2017

    Sheathing and Nailing Inspection

    Inspected by Troy Crews

  10. May 10, 2017

    Framing Inspection

    Inspected by Troy Crews

  11. May 10, 2017

    Rough-In Plumbing Inspection

    Inspected by Troy Crews

  12. May 10, 2017

    Electrical Rough-In Inspection

    Inspected by Troy Crews

  13. May 10, 2017

    Heat and Air Duct Inspection

    Inspected by Troy Crews

  14. May 12, 2017

    Insulation Inspection

    Inspected by Randy Jones

  15. May 12, 2017

    Insulation Inspection

    Inspected by Randy Jones

  16. Jun 27, 2017

    Permanent Power Inspection

    Inspected by Troy Crews

  17. Aug 14, 2017

    Final Inspection

    Inspected by Troy Crews

  18. Aug 15, 2017

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE