Permit Details

Permit Search

Permit

New Residential Construction

130 SW MORNING GLORY DR LAKE CITY FL 33024

Permit #
000034886
Application #
20941
Status Completed
  1. Submitted Jan 30, 2017
  2. Issued Jan 30, 2017
  3. Expires Sep 19, 2018
  4. Completed Mar 23, 2018

Property

Parcel #
03023-558
Owner
Joseph Drummond Ii.
Acres
0.50
Subdivision
Rolling Meadows
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0289D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
2919.00
Total Area (Sqft)
2937.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
17-0012-N

Status & Review History

No status updates yet.

Contractors

  • Jerry Castagna

    Castagna Construction,inc.

    License
    CBC047842
    Title
    Building Contractor
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Feb 6, 2017

    Foundation Inspection

    Inspected by Troy Crews

  2. Feb 6, 2017

    Setback Inspection

    Inspected by Troy Crews

  3. Feb 24, 2017

    Underslab Rough Plumbing Inspection

    Inspected by Troy Crews

  4. Feb 28, 2017

    Slab Inspection

    Inspected by Troy Crews

  5. Jul 18, 2017

    Sheathing and Nailing Inspection

    Inspected by Troy Crews

  6. Nov 20, 2017

    Rough-In Plumbing Inspection

    Inspected by Tommy Matthews

  7. Nov 20, 2017

    Electrical Rough-In Inspection

    Inspected by Tommy Matthews

  8. Nov 21, 2017

    Heat and Air Duct Inspection

    Inspected by Troy Crews

  9. Nov 21, 2017

    Framing Inspection

    Inspected by Troy Crews

  10. Nov 21, 2017

    Passed: Building - Framing

    Picked Up Revisions

    Inspected by Troy Crews

  11. Nov 21, 2017

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  12. Nov 21, 2017

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  13. Nov 21, 2017

    Passed: Plumbing/Gas - Water Pipe

    Inspected by Troy Crews

  14. Nov 27, 2017

    Insulation Inspection

    Inspected by Troy Crews

  15. Nov 27, 2017

    Passed: Building - Insulation

    Inspected by Troy Crews

  16. Feb 20, 2018

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  17. Mar 13, 2018

    Release to power company

    Inspected by Jlw

  18. Mar 13, 2018

    Septic Release Inspection

    Inspected by Health Dept

  19. Mar 23, 2018

    Final Inspection

    Inspected by Tommy Matthews

  20. Mar 23, 2018

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE

  21. Mar 23, 2018

    Passed: Building - Final

    Inspected by Tommy Matthews