| Temporary Power Inspection |
|
Randy Jones |
12/20/2016 |
| Setback Inspection |
|
Randy Jones |
12/20/2016 |
| Temporary Power Inspection |
|
Randy Jones |
12/20/2016 |
| Setback Inspection |
|
Randy Jones |
12/20/2016 |
| Foundation Inspection |
|
Randy Jones |
12/21/2016 |
| Foundation Inspection |
|
Randy Jones |
12/21/2016 |
| Underslab Rough Plumbing Inspection |
|
Troy Crews |
1/5/2017 |
| Slab Inspection |
|
Tommy Matthews |
1/12/2017 |
| Sheathing and Nailing Inspection |
|
Tommy Matthews |
2/1/2017 |
| Framing Inspection |
|
Troy Crews |
2/14/2017 |
| Rough-In Plumbing Inspection |
|
Troy Crews |
2/14/2017 |
| Electrical Rough-In Inspection |
|
Troy Crews |
2/14/2017 |
| Heat and Air Duct Inspection |
|
Troy Crews |
2/14/2017 |
| Insulation Inspection |
|
Tommy Matthews |
2/21/2017 |
| Permanent Power Inspection |
|
Troy Crews |
4/20/2017 |
| CERTIFICATE OF OCCUPANCY/COMPLETION DATE |
|
|
5/15/2017 |
| Final Inspection |
|
Troy Crews |
5/15/2017 |
| (Requested) Slab |
|
|
|
| (Requested) Sheathing/Nailing |
|
|
|
| (Requested) Slab |
|
|
|
| (Requested) Insulation |
|
|
|
| (Requested) Perm Power |
|
|
|
| (Requested) Perm Power |
|
|
|
| (Requested) Final |
|
|
|