Permit Details

Permit Search

Permit

New Residential Construction

281 SW NEWLYWED CT LAKE CITY FL 32024

Permit #
000033871
Application #
25446
Status Completed
  1. Submitted Mar 21, 2016
  2. Issued Mar 21, 2016
  3. Expires Sep 17, 2016
  4. Completed Aug 26, 2016

Property

Parcel #
02973-115
Owner
Bullard Management Services
Acres
0.50
Subdivision
Hunnington
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0293D
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1780.00
Total Area (Sqft)
2464.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Septic# (00-0000) or (X00-000)
16-0148

Status & Review History

No status updates yet.

Contractors

  • Adam Papka

    Adam's Construction Llc

    License
    CBC1253409
    Title
    Building Contractor
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Mar 24, 2016

    Foundation Inspection

    Inspected by Troy Crews

  2. Mar 24, 2016

    Setback Inspection

    Inspected by Troy Crews

  3. Mar 30, 2016

    Underslab Rough Plumbing Inspection

    Inspected by Troy Crews

  4. Apr 5, 2016

    Slab Inspection

    Inspected by Tommy Matthews

  5. Apr 22, 2016

    Sheeting and Nailing Inspection

    Inspected by Troy Crews

  6. Apr 22, 2016

    Sheathing and Nailing Inspection

    Inspected by Troy Crews

  7. May 9, 2016

    Framing Inspection

    Inspected by Tommy Matthews

  8. May 9, 2016

    Rough-In Plumbing Inspection

    Inspected by Tommy Matthews

  9. May 9, 2016

    Electrical Rough-In Inspection

    Inspected by Tommy Matthews

  10. May 9, 2016

    Heat and Air Duct Inspection

    Inspected by Tommy Matthews

  11. Jul 21, 2016

    Permanent Power Inspection

    Inspected by Tommy Matthews

  12. Aug 26, 2016

    Final Inspection

    Inspected by Troy Crews

  13. Aug 29, 2016

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE