Permit Details

Permit Search

Permit

New Residential Construction

758 NW BRIDGEWATER TERR LAKE CITY FL 32055

Permit #
000033379
Application #
25432
Status Completed
  1. Submitted Sep 17, 2015
  2. Issued Sep 17, 2015
  3. Expires Mar 15, 2016
  4. Completed Mar 4, 2016

Property

Parcel #
02275-119
Owner
Arthur & Joann Heath
Acres
2.05
Subdivision
Cobblestone
Zoning
RSF-2
Flood zone
A
District
1

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0283D
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
2008.00
Total Area (Sqft)
2546.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Septic# (00-0000) or (X00-000)
15-0450

Status & Review History

No status updates yet.

Contractors

  • Blake Lunde

    Blake Construction Company Of North Florida Inc

    License
    CBC1253408
    Title
    Building Contractor
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Sep 18, 2015

    Foundation Inspection

    Inspected by Tommy Matthews

  2. Sep 21, 2015

    Setback Inspection

    Inspected by Tommy Matthews

  3. Sep 22, 2015

    Temporary Power Inspection

    Inspected by Troy Crews

  4. Sep 24, 2015

    Underslab Rough Plumbing Inspection

    Inspected by Troy Crews

  5. Sep 30, 2015

    Slab Inspection

    Inspected by Troy Crews

  6. Oct 28, 2015

    Sheeting and Nailing Inspection

    Inspected by Troy Crews

  7. Oct 28, 2015

    Sheathing and Nailing Inspection

    Inspected by Troy Crews

  8. Nov 18, 2015

    Framing Inspection

    Inspected by Troy Crews

  9. Nov 18, 2015

    Rough-In Plumbing Inspection

    Inspected by Troy Crews

  10. Nov 18, 2015

    Electrical Rough-In Inspection

    Inspected by Troy Crews

  11. Nov 18, 2015

    Heat and Air Duct Inspection

    Inspected by Troy Crews

  12. Dec 15, 2015

    Insulation Inspection

    Inspected by Troy Crews

  13. Feb 15, 2016

    Permanent Power Inspection

    Inspected by Troy Crews

  14. Mar 4, 2016

    Final Inspection

    Inspected by Troy Crews

  15. Mar 4, 2016

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE

  16. Requested

    Above slab Rough-in

    Awaiting inspection

  17. Requested

    Electrical Rough-in

    Awaiting inspection

  18. Requested

    Framing

    Awaiting inspection

  19. Requested

    Heat & AC

    Awaiting inspection

  20. Requested

    Sheathing/Nailing

    Awaiting inspection

  21. Requested

    Insulation

    Awaiting inspection