Permit Details

Permit Search

Permit

New Residential Construction

1628 SW MANDIBA DR
LAKE CITY, FL 32024

Permit #
000032639
Application #
25408
Status Completed
  1. Submitted Jan 22, 2015
  2. Issued Jan 22, 2015
  3. Expires Jul 21, 2015
  4. Completed Sep 3, 2015

Property

Parcel #
09157-001
Owner
Rimrock Development Inc
Acres
20.07
Subdivision
—
Zoning
PRRD
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0395C
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
2
Heated Area (Sqft)
10952.00
Total Area (Sqft)
13691.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Septic# (00-0000) or (X00-000)
14-0501

Status & Review History

No status updates yet.

Contractors

  • Joel Phinney

    Skyline Construction Inc

    License
    CBC1256243
    Title
    Building Contractor
    Role
    —

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

Inspections

  1. Jan 22, 2015

    Temporary Power Inspection

    Inspected by Troy Crews

  2. Jan 23, 2015

    Foundation Inspection

    Inspected by Troy Crews

  3. Jan 23, 2015

    Setback Inspection

    Inspected by Troy Crews

  4. Jan 30, 2015

    Underslab Rough Plumbing Inspection

    Inspected by Troy Crews

  5. Feb 5, 2015

    Slab Inspection

    Inspected by Troy Crews

  6. Feb 19, 2015

    Perimeter Beam/Column Inspection

    Inspected by Troy Crews

  7. Mar 23, 2015

    Sheeting and Nailing Inspection

    Inspected by Troy Crews

  8. Mar 23, 2015

    Sheathing and Nailing Inspection

    Inspected by Troy Crews

  9. May 11, 2015

    Framing Inspection

    Inspected by Troy Crews

  10. May 11, 2015

    Rough-In Plumbing Inspection

    Inspected by Troy Crews

  11. May 11, 2015

    Heat and Air Duct Inspection

    Inspected by Troy Crews

  12. May 14, 2015

    Electrical Rough-In Inspection

    Inspected by Troy Crews

  13. May 18, 2015

    Insulation Inspection

    Inspected by Troy Crews

  14. Jul 28, 2015

    Permanent Power Inspection

    Inspected by Randy Jones

  15. Jul 28, 2015

    Permanent Power Inspection

    Inspected by Randy Jones

  16. Sep 3, 2015

    Final Inspection

    Inspected by Troy Crews

  17. Sep 3, 2015

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE

  18. Requested

    Under Slab Rough-in

    Awaiting inspection

  19. Requested

    Beam (Lintel) - Tie Beam

    Awaiting inspection

  20. Requested

    Beam (Lintel) - Tie Beam

    Awaiting inspection

  21. Requested

    Beam (Lintel) - Tie Beam

    Awaiting inspection