Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit
Address 588 SW PINEHURST DR LAKE CITY FL 32024
Parcel #: 03087-118
Acres: 0.73
Owner: Michael & Patricia Roper
Subdivision: Forest Country 6th Addition
Zoning: RSF-2
Flood Zone: X PP
District: 3
Application #: 25364
Permit #: 000031497
Related Permit: Culvert: 000002044
Submitted: Monday, October 7, 2013
Issued: Monday, October 7, 2013
Expires: Tuesday, September 9, 2014
Completed: Tuesday, September 9, 2014
Status: Completed
Septic Release? No
Notes:
MINIMUM FLOOR ELEVATION SET @ 109.7 PER S/D PLAT, NEED ELEVATION CONFIRMATION LETTER AT SLAB, LETTER REC'D @ 112.10' NOC ON FILE TERMITE TREATMENT REC'D
Job Details
This is the construction of a SFD, UTILITY
Heated Area (Sqft) 2620.00
Total Area (Sqft) 3680.00
Stories 1
Setbacks Front 25.00
Setback Side 1 10.00
Setback Side 2 10.00
Setbacks Rear 15.00
Building Code Edition Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Fema map number 12023C0289D
Review Notes
Contractors
Name/ Business License Title Role
Glenwood King
Glenwood King Construction, Inc.
CBC059726 Building Contractor
Inspections
Inspection Notes Performed By Date
Foundation Inspection Troy Crews 1/14/2013
Passed: Engineering - Initial Driveway Cm 10/9/2013
Temporary Power Inspection Randy Jones 10/11/2013
Temporary Power Inspection Randy Jones 10/11/2013
Foundation Inspection Troy Crews 10/14/2013
Setback Inspection Troy Crews 10/14/2013
Perimeter Beam/Column Inspection Troy Crews 10/16/2013
Rough-In Plumbing Inspection Troy Crews 11/1/2013
Underslab Rough Plumbing Inspection Troy Crews 11/1/2013
Slab Inspection Troy Crews 11/7/2013
Sheeting and Nailing Inspection Troy Crews 12/9/2013
Sheathing and Nailing Inspection Troy Crews 12/9/2013
Framing Inspection Troy Crews 1/15/2014
Rough-In Plumbing Inspection Troy Crews 1/15/2014
Electrical Rough-In Inspection Troy Crews 1/15/2014
Heat and Air Duct Inspection Troy Crews 1/15/2014
Insulation Inspection Troy Crews 1/29/2014
Permanent Power Inspection Randy Jones 5/27/2014
Permanent Power Inspection Randy Jones 5/27/2014
Final Inspection Troy Crews 9/9/2014
CERTIFICATE OF OCCUPANCY/COMPLETION DATE 9/9/2014