Permit Details

Permit Search

Permit

New Commercial Construction

1658 W US HIGHWAY 90 LAKE CITY FL 32055

Permit #
000031152
Application #
32348
Status Completed
  1. Submitted Jun 19, 2013
  2. Issued Jun 19, 2013
  3. Expires Dec 16, 2013
  4. Completed Dec 12, 2013

Property

Parcel #
06219-001
Owner
Campus Usa Credit Union
Acres
2.13
Subdivision
Ridgewood Manor
Zoning
CI
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0291D
This is the construction of a:
COMMERCIAL BANK
Setbacks Front
20.00
Setback Side 1
15.00
Setback Side 2
15.00
Setback Rear
0.00
Stories
1
Heated Area (Sqft)
4720.00
Total Area (Sqft)
8001.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code

Status & Review History

No status updates yet.

Contractors

  • Douglas W. Wilcox,ii.

    Scherer Construction Of N Fl Llc

    License
    CGC057622
    Title
    General Contractor
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Jul 25, 2013

    Temporary Power Inspection

    Inspected by Troy Crews

  2. Jul 26, 2013

    Underslab Rough Plumbing Inspection

    Inspected by Randy Jones

  3. Jul 26, 2013

    Underslab Rough Plumbing Inspection

    Inspected by Randy Jones

  4. Jul 30, 2013

    Electrical Rough-In Inspection

    Inspected by Randy Jones

  5. Jul 30, 2013

    Electrical Rough-In Inspection

    Inspected by Randy Jones

  6. Aug 1, 2013

    Monolithic Slab Inspection

    Inspected by Randy Jones

  7. Aug 1, 2013

    Setback Inspection

    Inspected by Randy Jones

  8. Aug 1, 2013

    Monolithic Slab Inspection

    Inspected by Randy Jones

  9. Aug 27, 2013

    Perimeter Beam/Column Inspection

    Inspected by Troy Crews

  10. Sep 10, 2013

    Sheeting and Nailing Inspection

    Inspected by Troy Crews

  11. Sep 10, 2013

    Sheathing and Nailing Inspection

    Inspected by Troy Crews

  12. Sep 13, 2013

    Framing Inspection

    Inspected by Troy Crews

  13. Sep 18, 2013

    Insulation Inspection

    Inspected by Troy Crews

  14. Sep 30, 2013

    Heat and Air Duct Inspection

    Inspected by Troy Crews

  15. Nov 13, 2013

    Permanent Power Inspection

    Inspected by Troy Crews

  16. Dec 12, 2013

    Final Inspection

    Inspected by Troy Crews

  17. Dec 12, 2013

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE

  18. Requested

    Slab

    Awaiting inspection

Documents