Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit
Address 325 NW HIGH-POINT-DRIVE
LAKE CITY, FL 32055
Parcel #: 02203-004
Acres: 4.80
Owner: Kevin & Heather Gray
Subdivision:
Zoning: PRRD
Flood Zone: X
District:
Application #: 20551
Permit #: 000025512
Related Permit:
Submitted: Monday, February 12, 2007
Issued: Monday, February 12, 2007
Expires: Friday, November 2, 2007
Completed: Friday, November 2, 2007
Status: Completed
Septic Release? No
Notes:
NOC ON FILE. 1 FOOT ABOVE ROAD.PENDING SIGNED DEVELOPMENT AGREEMENT FROM PROPERTY OWNER & DEVELOPER PER COUNTY MANAGER, CO ISSUED PER COUNTY MANAGER,NO AGREEMENT IS REQUIRED AS S/D PLATTED PRIOR TO CO
Job Details
This is the construction of a SFD/UTILITY
Heated Area (Sqft) 3407.00
Total Area (Sqft) 4930.00
Stories 1
Setbacks Front 30.00
Setback Side 1 25.00
Setback Side 2 25.00
Setbacks Rear 25.00
Building Code Edition Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Review Notes
Contractors
Name/ Business License Title Role
Glenwood King
Glenwood King Construction, Inc.
CBC059726 Building Contractor
Inspections
Inspection Notes Performed By Date
Foundation Inspection Harry Dicks 2/19/2007
Setback Inspection Harry Dicks 2/19/2007
Underslab Rough Plumbing Inspection Harry Dicks 2/27/2007
Slab Inspection Randy Jones 3/1/2007
Slab Inspection Randy Jones 3/1/2007
Sheeting and Nailing Inspection Harry Dicks 4/9/2007
Sheathing and Nailing Inspection Harry Dicks 4/9/2007
Rough-In Plumbing Inspection John Kerce 5/15/2007
Electrical Rough-In Inspection John Kerce 5/15/2007
Heat and Air Duct Inspection John Kerce 5/15/2007
Framing Inspection Randy Jones 5/17/2007
Framing Inspection Randy Jones 5/17/2007
Permanent Power Inspection Randy Jones 9/4/2007
Permanent Power Inspection Randy Jones 9/4/2007
Final Inspection Harry Dicks 11/2/2007
CERTIFICATE OF OCCUPANCY/COMPLETION DATE 11/5/2007