| Foundation Inspection |
|
Harry Dicks |
12/6/2005 |
| Setback Inspection |
|
Harry Dicks |
12/6/2005 |
| Temporary Power Inspection |
|
Harry Dicks |
12/14/2005 |
| Underslab Rough Plumbing Inspection |
|
Randy Jones |
12/16/2005 |
| Underslab Rough Plumbing Inspection |
|
Randy Jones |
12/16/2005 |
| Slab Inspection |
|
Randy Jones |
12/21/2005 |
| Slab Inspection |
|
Randy Jones |
12/21/2005 |
| Perimeter Beam/Column Inspection |
|
Randy Jones |
1/4/2006 |
| Perimeter Beam/Column Inspection |
|
Randy Jones |
1/4/2006 |
| Sheeting and Nailing Inspection |
|
Randy Jones |
1/27/2006 |
| Sheathing and Nailing Inspection |
|
Randy Jones |
1/27/2006 |
| Sheathing and Nailing Inspection |
|
Randy Jones |
1/27/2006 |
| Framing Inspection |
|
Randy Jones |
2/15/2006 |
| Rough-In Plumbing Inspection |
|
Randy Jones |
2/15/2006 |
| Electrical Rough-In Inspection |
|
Randy Jones |
2/15/2006 |
| Heat and Air Duct Inspection |
|
Randy Jones |
2/15/2006 |
| Framing Inspection |
|
Randy Jones |
2/15/2006 |
| Permanent Power Inspection |
|
Randy Jones |
3/31/2006 |
| Permanent Power Inspection |
|
Randy Jones |
3/31/2006 |
| Final Inspection |
|
Randy Jones |
4/26/2006 |
| CERTIFICATE OF OCCUPANCY/COMPLETION DATE |
|
|
4/26/2006 |
| Final Inspection |
|
Randy Jones |
4/26/2006 |