Mobile Home
Permit
| Application #: | 75781 |
| Permit #: |
000055698 |
| Related Permit: |
|
| Submitted: | Monday, May 4, 2026 |
| Issued: | Friday, May 15, 2026 |
| Expires: | Wednesday, November 11, 2026 |
| Completed: | |
| Status: |
Permit Issued |
| Septic Release? |
No |
Notes
*SDP260201
*MFE = BOTTOM OF LOWEST BEAM MUST BE 1' ABOVE THE ROAD
*FINAL DOT APPROVAL REQUIRED PRIOR TO FINAL, REQUEST THROUGH COUNTY
*CITY TAP INSPECTION REQUIRED PRIOR TO FINAL, REQUEST THROUGH COUNTY
*ADA RAMP AND DESIGNATED PARKING SPACE REQUIRED
LAKE CITY UTLITY CUSTOMER SERVICE NOTES
05/15/26 Locates must be obtained to ensure that the existing utility infrastructure is not damaged or obstructed. I asked Brody Pack whether they are connecting at the water meter and sewer tap, or at their private plumbing. He is going to find out and let us know. Depending on the answer, a utility inspection may be required.