Permit Details

Permit Search

Permit

Roof Replacement or Repair

943 SE ALFRED MARKHAM ST
LAKE CITY, FL 32025

Permit #
000055018
Application #
74960
Status Completed
  1. Submitted Jan 27, 2026
  2. Issued Feb 13, 2026
  3. Expires Nov 11, 2026
  4. Completed May 15, 2026

Property

Parcel #
08951-001
Owner
Christie Chad, Christie Kayla
Acres
1.80
Subdivision
—
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
N/A
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0405C
Type Roofing Job
Overlay with Metal
Type of structure
House
Commercial or Residential
Residential
Roof Area (for this job) Sq Ft
2600
No. of Stories
1
Roof Pitch
2:12 to 4:12
Is the existing roof being removed?
No
Explain if not removing the existing roofing material?
Metal over shingles
Type of New Roofing Product
Metal
Florida Product Approval Number
25681
Product Manufacturer
Millenium metals
Product Description
Roofing metal
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Sealed roof decking options: (Must select an option.)
Other (explain)
Sealed roof decking explanation for other option.
Metal over shingles
Ventilation:
Ridge Vent
Flashing:
Replace with L-Flashing
Drip Edge:
Replace All
Valley Treatment:
New Metal
Any cable and/or race-way wiring located on or within the roof assembly?
No

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Application Status Update Notification
  4. Application submitted by applicant.
  5. Application Status Update Notification
  6. Application submitted by applicant.
  7. Application Status Update Notification
  8. Recorded Notice of Commencement was not accepted.
  9. Application Status Update Notification
  10. Recorded Notice of Commencement was not accepted.
  11. Application Status Update Notification
  12. Application Status Update Notification
  13. Permit Issued

Contractors

This is an owner-builder project.

Inspections

  1. Mar 26, 2026

    Passed: Re-Roof - In Progress

    Inspected by Troy Crews

  2. Apr 9, 2026

    Passed: Re-Roof - Roof Pictures Review

    Inspected by Troy Crews

  3. May 15, 2026

    Passed: Re-Roof - Final

    Inspected by Troy Crews