| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
3/9/2026 |
| Rescheduled 3/17/2026:Building - Monolithic Slab |
|
Tcrews |
3/16/2026 |
| Rescheduled 3/17/2026:Engineering - Setbacks |
|
Tcrews |
3/16/2026 |
| Rescheduled 3/17/2026:Electrical - Footer Steel & Grounding |
|
Tcrews |
3/16/2026 |
| Passed: Building - Monolithic Slab |
|
Troy Crews |
3/17/2026 |
| Passed: Engineering - Setbacks |
Setbacks To Be Confirmed By Surveyor |
Troy Crews |
3/17/2026 |
| Passed: Electrical - Footer Steel & Grounding |
|
Troy Crews |
3/17/2026 |
| Passed: Building - Roof Decking |
|
Troy Crews |
3/31/2026 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
3/31/2026 |
| Cancelled: Building - Ext Strapping/Wall Sheathing |
Already Done |
Tcrews |
4/9/2026 |
| Failed: Building - Framing |
No Windows Installed |
Troy Crews |
4/9/2026 |
| Failed: Electrical - 2nd Rough-In |
Bath Fans Not Wired In |
Troy Crews |
4/9/2026 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
4/9/2026 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
4/9/2026 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Troy Crews |
4/9/2026 |
| Passed: Building - Framing |
Windows Installed |
Troy Crews |
4/16/2026 |
| Passed: Electrical - 2nd Rough-In |
Bath Fans Now Wired In |
Troy Crews |
4/16/2026 |
| Passed: Building - Insulation |
|
Troy Crews |
4/16/2026 |
| Passed: City of Lake City Utilities - Lake City Utilities Tap Inspection |
|
City Of Lake City Distribution And Collections Department |
6/4/2026 |
| Failed: Electrical - Permanent Power |
Electrical Not Trimmed Out Ground Wire Service Not Connected No Grounding Block Also Need City Tap Inspection |
Troy Crews |
6/5/2026 |
| Passed: Electrical - Permanent Power |
*all Requirements Met To Release Power -- 6.11.26 Mg |
Troy Crews |
6/10/2026 |
| Release to power company |
*all Requirements Met To Release Power -- 6.11.26 Mg |
Troy Crews |
6/10/2026 |
| Submitted Power Release through FPL Portal |
|
Garber, Melissa |
6/11/2026 |