Permit Details

Permit Search

Permit

New Residential Construction

341 SW PINEHURST DR
LAKE CITY, FL 32024

Permit #
000054869
Application #
74724
Status Permit Status Update Notification
  1. Submitted Jan 13, 2026
  2. Issued Jan 22, 2026
  3. Expires Mar 29, 2027
  4. Completed —

Property

Parcel #
03087-108
Owner
Sparks Josh,
Acres
0.68
Subdivision
Forest Country Sixth Addition
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Permit Status Update Notification
Septic release
Not yet released
Related permit
—

Job Details

Elevation regulation
Engineers Elevation Letter
Finished floor requirement
88.5 NA
Requirement needed
Slab Inspection
Document needed is
Surveyor letter (FFE)
Document receieved
Yes
Fema map number
12023C0289D
This is the construction of a
Single Family Dwelling
Setbacks Front
20'
Setback Side 1
15'
Setback Side 2
15'
Setbacks Rear
10'
Stories
2
Heated Area (Sqft)
3109
Total Area (Sqft)
4856
Building Height
27.2
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
25-0917
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
220

Status & Review History

  1. Application pending.
  2. Architectural Plans was not accepted.
  3. Recorded Notice of Commencement was not accepted.
  4. Application Status Update Notification
  5. Submitted by building department on applicant's behalf
  6. Application Status Update Notification
  7. Application Status Update Notification
  8. Application Status Update Notification
  9. Permit Issued
  10. Permit Status Update Notification
  11. Permit Status Update Notification

Contractors

  • Benjamin L Sparks

    Line Electric Company Llc

    License
    EC13009101
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License Expired.

  • Clinton G Wilson

    Wilson Heat & Air Inc

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Ralph W Laverdure

    Rwl Roofing Llc

    License
    CCC1328590
    Title
    Roofing Contractor
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Josh Sparks

    Sparks Construction

    License
    CBC1252260
    Title
    Building Contractor
    Role
    Contractor
  1. Mar 30, 2026

    Passed: Building - Footer

    Inspected by Matt Forsyth

  2. Mar 30, 2026

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  3. Mar 30, 2026

    Passed: Electrical - Footer Steel & Grounding

    Inspected by Matt Forsyth

  4. Apr 23, 2026

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Waste Pipe Only

    Inspected by Matt Forsyth

  5. May 6, 2026

    Passed: Building - Slab

    Pictures Of Hook Bar Chaired Up Needed Before Pouring Cement

    Inspected by Matt Forsyth

  6. Jun 24, 2026

    Passed: Building - Ext Strapping/Wall Sheathing

    Simpson 8in Screws Gable Ends

    Inspected by Matt Forsyth

  7. Jun 24, 2026

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  8. Jun 24, 2026

    Passed: Building - Wall Sheathing

    Inspected by Matt Forsyth

  9. Aug 21, 2026

    Passed: Building - Framing

    Inspected by Matt Forsyth

  10. Aug 21, 2026

    Passed: Electrical - Temporary Power Service

    Inspected by Matt Forsyth

  11. Aug 25, 2026

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Matt Forsyth

  12. Aug 25, 2026

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  13. Aug 25, 2026

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  14. Aug 25, 2026

    Cancelled: Electrical - 1st Underground Rough–In

    Inspected by Mforsyth

  15. Aug 27, 2026

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  16. Sep 1, 2026

    Release to power company

    Temp Power Only

    Inspected by Ewilliams

  17. Sep 2, 2026

    Cancelled: Electrical - 1st Underground Rough–In

    Already Done

    Inspected by Tcrews

  18. Sep 30, 2026

    Passed: Building - Insulation

    Inspected by Matt Forsyth

  19. Requested

    Building - Insulation

    Awaiting inspection

Documents