| Septic Release Inspection |
|
Health Dept |
12/10/2025 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Waste Pipe On Top Of Existing Garage Floor |
Matt Forsyth |
1/30/2026 |
| Passed: Building - Footer |
Monolithic Slab |
Matt Forsyth |
2/18/2026 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
2/18/2026 |
| Passed: Electrical - 1st Underground Rough–In |
Floor Mount |
Matt Forsyth |
2/18/2026 |
| Passed: Building - Slab |
8 Inch Slab Garage Suggested Expansion Joint Around Perimeter Of Garage |
Matt Forsyth |
2/18/2026 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
3/5/2026 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
3/5/2026 |
| Passed: Building - Roof Decking |
|
Troy Crews |
3/5/2026 |
| Passed: Building - Framing |
Look For Truss Clips On Electrical Rough In Inspection |
Troy Crews |
3/5/2026 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
3/16/2026 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
3/16/2026 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
3/16/2026 |
| Failed: Mechanical - Rough In |
|
Matt Forsyth |
3/16/2026 |
| Passed: Mechanical - Rough In |
Item Addressed |
Matt Forsyth |
3/18/2026 |
| Passed: Building - Insulation |
Final Should Not Have Been Passed Due To Windows Being On Back Order, Therefore, It Has Been Removed. Please Call Or Visit Our Website To Reshedule The Final Once Windows Have Arrived And Are Installed-- 5.26.26 Mg/tc |
Matt Forsyth |
3/23/2026 |
| Cancelled: Building - Final |
Removed/cancelled Due To Windows Being On Back Order-- 5.26.26 Mg |
Mgarber |
5/26/2026 |
| Passed: Building - Final |
*all Requirements Met To Release Co-- 7.7.26 Mg |
Matt Forsyth |
7/6/2026 |