Permit Details

Permit Search

Permit

New Residential Construction

170 SW HIGH FIELD TER
LAKE CITY, FL 32024

Permit #
000054742
Application #
73542
Status Permit Issued
  1. Submitted Oct 1, 2025
  2. Issued Dec 30, 2025
  3. Expires May 11, 2027
  4. Completed —

Property

Parcel #
03761-173
Owner
Rivera Carlos L Vilma M Rivera Trsut Dated November 22, 2023,
Acres
5.89
Subdivision
Meadowlands Phase 4
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Permit Issued
Septic release
Not yet released
Related permit
—

Job Details

Elevation regulation
Subdivision Plat
Finished floor requirement
88.7'
Requirement needed
By Nailing Inspection
Document needed is
Surveyor letter (FFE)
Document receieved
Yes
Fema map number
12023C0485C
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
1750
Total Area (Sqft)
2250
Building Height
1
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
25-0783
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
Other (explain)
Sealed roof decking explanation for other option.
part of metal building
Service Amps
200

Status & Review History

  1. Application pending.
  2. Point Review - Contact the Building Dept
  3. Point Review - Pre-submittal Review Notes
  4. Point Review - Pre-submittal Review Notes
  5. Point Review - Pre-submittal Review Notes
  6. Point Review-Corrections Needed
  7. Point Review - Ready for applicant submittal
  8. Point Review - Ready for applicant submittal
  9. Application submitted by applicant.
  10. Application submitted by applicant.
  11. Zoning Review - Sent for Zoning Review
  12. Plan Review - Sent to plan review
  13. Application Status Update Notification
  14. Application Status Update Notification
  15. Application Status Update Notification
  16. Application Status Update Notification
  17. Application Status Update Notification
  18. Application Status Update Notification
  19. Application Status Update Notification
  20. Application Status Update Notification
  21. Application Status Update Notification
  22. Application Status Update Notification
  23. Application Status Update Notification
  24. Application Status Update Notification
  25. Application Status Update Notification
  26. Application Status Update Notification
  27. Application Status Update Notification
  28. Permit Issued

Contractors

This is an owner-builder project.

  1. Feb 18, 2026

    Passed: Electrical - Temporary Power Service

    For Temp Use Only

    Inspected by Gary Pitzer

  2. Feb 18, 2026

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Ok To Move Forward On Slab Work

    Inspected by Gary Pitzer

  3. Feb 20, 2026

    Passed: Engineering - Setbacks

    Near Middle Of Lot

    Inspected by Gary Pitzer

  4. Feb 20, 2026

    Passed: Electrical - Footer Steel & Grounding

    Inspected by Gary Pitzer

  5. Feb 20, 2026

    Passed: Building - Monolithic Slab

    Inspected by Gary Pitzer

  6. Feb 20, 2026

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Gary Pitzer

  7. Mar 12, 2026

    Release to power company

    Inspected by Tcrews

  8. Jul 29, 2026

    Passed: Building - Framing

    Steel Building Framing

    Inspected by Troy Crews

  9. Nov 12, 2026

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  10. Nov 12, 2026

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  11. Nov 12, 2026

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Troy Crews

Documents