| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
3/9/2026 |
| Passed: Building - Monolithic Slab |
Clear Rain Water From Found Contractor To Send Pictures |
Troy Crews |
3/16/2026 |
| Passed: Electrical - Footer Steel & Grounding |
|
Troy Crews |
3/16/2026 |
| Passed: Engineering - Setbacks |
Setbacks To Be Confirmed By Surveyor |
Troy Crews |
3/16/2026 |
| Rescheduled 3/19/2026:Building - Monolithic Slab |
|
Tcrews |
3/18/2026 |
| Rescheduled 3/19/2026:Electrical - Footer Steel & Grounding |
|
Tcrews |
3/18/2026 |
| Rescheduled 3/19/2026:Engineering - Setbacks |
|
Tcrews |
3/18/2026 |
| Cancelled: Building - Monolithic Slab |
|
Tcrews |
3/19/2026 |
| Cancelled: Engineering - Setbacks |
|
Tcrews |
3/19/2026 |
| Cancelled: Electrical - Footer Steel & Grounding |
|
Tcrews |
3/19/2026 |
| Passed: Building - Monolithic Slab |
|
Troy Crews |
3/23/2026 |
| Passed: Electrical - Footer Steel & Grounding |
|
Troy Crews |
3/23/2026 |
| Passed: Engineering - Setbacks |
Setbacks To Be Confirmed By Surveyor |
Troy Crews |
3/23/2026 |
| Passed: Building - Roof Decking |
|
Troy Crews |
4/8/2026 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
4/8/2026 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
4/8/2026 |
| Passed: Building - Framing |
|
Troy Crews |
4/21/2026 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
4/21/2026 |
| Failed: Electrical - 2nd Rough-In |
Bath Fans Not Wired In |
Troy Crews |
4/21/2026 |
| Failed: Plumbing/Gas - 2nd Rough-In |
No Pressure On Water Lines |
Troy Crews |
4/21/2026 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Troy Crews |
4/21/2026 |
| Passed: Building - Insulation |
|
Troy Crews |
4/30/2026 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
4/30/2026 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Pressure On |
Troy Crews |
4/30/2026 |