| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
2/4/2026 |
| Passed: Building - Monolithic Slab |
|
Troy Crews |
2/6/2026 |
| Passed: Electrical - Footer Steel & Grounding |
|
Troy Crews |
2/6/2026 |
| Passed: Engineering - Setbacks |
Setbacks To Be Confirmed By Surveyor |
Troy Crews |
2/6/2026 |
| Passed: Building - Roof Decking |
|
Troy Crews |
2/18/2026 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
2/18/2026 |
| Cancelled: Building - Ext Strapping/Wall Sheathing |
|
Tcrews |
2/24/2026 |
| Failed: Electrical - 2nd Rough-In |
Bath Fans Not Wired In Also No Main Service Entrance Cable Installed |
Troy Crews |
2/24/2026 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
2/24/2026 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
2/24/2026 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Troy Crews |
2/24/2026 |
| Failed: Building - Framing |
Check All Double Girders In House For Strapping |
Troy Crews |
2/24/2026 |
| Cancelled: Building - Ext Strapping/Wall Sheathing |
Already Done |
Tcrews |
2/26/2026 |
| Passed: Electrical - 2nd Rough-In |
Item Corrected |
Troy Crews |
2/26/2026 |
| Passed: Building - Framing |
Double Girders Strapped Off |
Troy Crews |
2/26/2026 |
| Passed: Building - Insulation |
|
Troy Crews |
2/26/2026 |
| Failed: City of Lake City Utilities - Lake City Utilities Tap Inspection |
Your Plumber Will Need To Contact Growth Management To Submit A Utility Connection Permit. Permit Technicians Can Assist You With Any Questions You May Have About The Permitting Process. Ms. Ivy Stockstill Can Be Reached At (386)719-5750 Or Francoi@lcfla.com, Or Ms. Kiana Williams Can Be Reached At 386-719-5751 Or Williamsk@lcfla.com.
once The Plumbing Is Connected To The Water Meter And Sewer Tap, A City Utility Inspector Must Inspect The Connection Before Covering The Connection Points. Please Call To Schedule An Inspection And Initial Turn-on Appointment. If The Request Is Received Before 1 Pm, The Appointment Can Be Scheduled For The Same Day. Any Requests Received After 1 Pm Will Be Scheduled For The Next Business Day.
|
City Of Lake City Tap And Impact Department |
4/15/2026 |
| Failed: Electrical - Permanent Power |
Ground Wire Clamp Loose And Ground From Foundation Not Connected |
Troy Crews |
4/16/2026 |
| Failed: City of Lake City Utilities - Lake City Utilities Tap Inspection |
Your Plumber Will Need To Contact Growth Management To Submit A Utility Connection Permit. Permit Technicians Can Assist You With Any Questions You May Have About The Permitting Process. Ms. Ivy Stockstill Can Be Reached At (386)719-5750 Or Francoi@lcfla.com, Or Ms. Kiana Williams Can Be Reached At 386-719-5751 Or Williamsk@lcfla.com.
once The Plumbing Is Connected To The Water Meter And Sewer Tap, A City Utility Inspector Must Inspect The Connection Before Covering The Connection Points. Please Call 386-719-5778 Or 386-719-5786 To Schedule An Inspection And Initial Turn-on Appointment. If The Request Is Received Before 1 Pm, The Appointment Can Be Scheduled For The Same Day. Any Requests Received After 1 Pm Will Be Scheduled For The Next Business Day. |
City Of Lake City Tap And Impact Department |
4/17/2026 |
| Passed: Electrical - Permanent Power |
Items Corrected Must Have Completed City Tap Inspection For Final Release |
Troy Crews |
4/20/2026 |