Permit Details

Permit Search

Permit

New Residential Construction

196 SW IVY GLN
LAKE CITY, FL 32024

Permit #
000054580
Application #
73602
Status Permit Reissued
  1. Submitted Oct 6, 2025
  2. Issued May 1, 2026
  3. Expires Nov 24, 2026
  4. Completed —

Property

Parcel #
03011-115
Owner
Gator Land Development, Llc,
Acres
0.28
Subdivision
Rose Pointe
Zoning
PRD
Flood zone
X
District
3

Permit

Status
Permit Reissued
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Subdivision Plat
Finished floor requirement
Minimum finished floor elevation = 109.0' or higher
Requirement needed
By Nailing Inspection
Document needed is
NA
Fema map number
12023C0289D
This is the construction of a
Single Family Dwelling
Setbacks Front
25'
Setback Side 1
10'
Setback Side 2
10'
Setbacks Rear
15'
Stories
1
Heated Area (Sqft)
1380
Total Area (Sqft)
1888
Building Height
17
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
25-0766
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. City of Lake City Utilities Notified.
  3. Point Review - Pre-submittal Review Notes
  4. Point Review - Pre-submittal Review Notes
  5. Point Review - Ready for applicant submittal
  6. Application submitted by applicant.
  7. City of Lake City Utilities Notified.
  8. Point Review - Processing
  9. Point Review - Complete
  10. Zoning Review - Sent for Zoning Review
  11. Plan Review - Plumbing Approved
  12. Plan Review - Mechanical Approved
  13. Plan Review - Electrical Approved
  14. Plan Review - Building Approved
  15. Plan Review - Reviewed
  16. Final Review - Processing
  17. Zoning Review - Sent for Zoning Review
  18. Zoning Review - Reviewed
  19. Final Review - Sent for final review
  20. Application Status Update Notification
  21. Application Status Update Notification
  22. Application Status Update Notification
  23. Application Status Update Notification
  24. Permit Issued
  25. Permit Reissued

Contractors

  • Joseph C Peurrung

    Benchmark Builders Llc

    License
    CBC1259347
    Title
    Cert. Building
    Role
    Contractor
  • Alaina Perry

    North Florida Maintenance And Repair Services Llc

    License
    EC13014792
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License Expired.

  • Benjamin T Keeler

    Keeler Roofing, Llc

    License
    CCC1330509
    Title
    Cert. Roofing
    Role
    Subcontractor
  • Clinton G Wilson

    Wilson Heat & Air Inc

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor
  1. Jan 8, 2026

    Passed: Electrical - Temporary Power Service

    Inspected by Matt Forsyth

  2. Jan 14, 2026

    Passed: Building - Footer

    Inspected by Matt Forsyth

  3. Feb 27, 2026

    Passed: Electrical - 1st Underground Rough–In

    Need Portal Let And Dumpster On Job Site

    Inspected by Matt Forsyth

  4. Feb 27, 2026

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Matt Forsyth

  5. Mar 3, 2026

    Release to power company

    Inspected by Ewilliams

  6. Mar 6, 2026

    Passed: Building - Slab

    Inspected by Matt Forsyth

  7. Apr 6, 2026

    Passed: Building - Wall Sheathing

    Inspected by Matt Forsyth

  8. Apr 6, 2026

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  9. Apr 6, 2026

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  10. May 7, 2026

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  11. May 7, 2026

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  12. May 18, 2026

    Passed: Electrical - 2nd Rough-In

    Nail Plates Needed Above Service Panel Inside Garage

    Inspected by Matt Forsyth

  13. May 19, 2026

    Passed: Building - Framing

    Inspected by Matt Forsyth

  14. May 19, 2026

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Matt Forsyth

  15. May 28, 2026

    Passed: Building - Insulation

    Water Supply Under Pressure Atd Inspection

    Inspected by Matt Forsyth

  16. Oct 19, 2026

    Septic Release Inspection

    Inspected by Health Dept

Documents