| 2/3/2025 |
Application pending. |
| 2/3/2025 |
Application submitted by applicant. |
| 2/24/2025 |
Point Review - Printed-Online Application |
| 2/24/2025 |
Point Review - Reviewed |
| 2/24/2025 |
Zoning Review - Reviewed |
| 2/25/2025 |
Plan Review - Reviewed |
| 2/27/2025 |
Final Review - Documents Required |
| 3/9/2025 |
Final Review - Documents Required |
| 3/14/2025 |
Final Review - Documents Required |
| 3/18/2025 |
Final Review - Documents Required |
| 3/25/2025 |
Final Review - Documents Required |
| 4/2/2025 |
Final Review - Documents Required |
| 4/25/2025 |
Final Review - Documents Required |
| 4/28/2025 |
Final Review - Documents Required |
| 5/5/2025 |
Final Review - Documents Required |
| 5/11/2025 |
Final Review - Documents Required |
| 5/18/2025 |
Final Review - Documents Required |
| 5/29/2025 |
Final Review - Documents Required |
| 6/3/2025 |
Final Review - Documents Required |
| 6/5/2025 |
Final Review - Payment Needed |
| 6/16/2025 |
Final Review - Payment Needed |
| 6/21/2025 |
Final Review - Payment Needed |
| 6/22/2025 |
Final Review - Payment Needed |
| 6/27/2025 |
Final Review - Payment Needed |
| 7/3/2025 |
Final Review - Payment Needed |
| 7/11/2025 |
Final Review - Payment Needed |
| 7/16/2025 |
Final Review - Payment Needed |
| 8/1/2025 |
Final Review - Payment Needed |
| 8/8/2025 |
Final Review - Payment Needed |
| 8/22/2025 |
Final Review - Payment Needed |
| 8/26/2025 |
Final Review - Payment Needed |
| 9/5/2025 |
Final Review - Payment Needed |
| 9/19/2025 |
Final Review - Payment Needed |
| 9/26/2025 |
Final Review - Payment Needed |
| 10/3/2025 |
Final Review - Payment Needed |
| 10/10/2025 |
Final Review - Payment Needed |
| 10/17/2025 |
Final Review - Payment Needed |
| 10/24/2025 |
Final Review - Payment Needed |
| 10/31/2025 |
Final Review - Application Returned |
| 10/31/2025 |
Application Voided |
| 10/31/2025 |
Application Un-Voided |
| 10/31/2025 |
Permit Issued |