Solar Power System
Permit
| Application #: | 72565 |
| Permit #: |
000054192 |
| Related Permit: |
|
| Submitted: | Monday, August 4, 2025 |
| Issued: | Wednesday, April 15, 2026 |
| Expires: | Thursday, April 16, 2026 |
| Completed: | Thursday, April 16, 2026 |
| Status: |
Completed |
| Septic Release? |
N/A |
Job Details
| Finished floor requirement |
|
| Fema map number |
12023C0280D |
| PV Type |
Utility Interactive PV System- (DC to AC with utility connection) |
| Grounding |
N.E.C. Chapter 690 |
| AC Options |
Exposed |
| AC Options (Cont..) |
In Conduit |
| Building Code Edition |
2023 Florida Building Code 8th Edition and 2020 National Electrical Code |
| Power Company |
Florida Power and Light |
| Residential or Commercial? |
Residential |
| Where are the panels mounted? |
Roof Mounted |
| Service Amps |
200 |
Review Notes
| 8/4/2025 |
Application pending. |
| 8/5/2025 |
Point Review - Pre-submittal Review Notes |
| 8/13/2025 |
Point Review - Pre-submittal Review Notes |
| 8/18/2025 |
Point Review - Pre-submittal Review Notes |
| 8/26/2025 |
Point Review - Pre-submittal Review Notes |
| 8/28/2025 |
Point Review - Pre-submittal Review Notes |
| 9/1/2025 |
Point Review - Pre-submittal Review Notes |
| 9/9/2025 |
Point Review - Pre-submittal Review Notes |
| 9/10/2025 |
Point Review - Pre-submittal Review Notes |
| 9/11/2025 |
Point Review - Pre-submittal Review Notes |
| 9/15/2025 |
Point Review - Pre-submittal Review Notes |
| 9/21/2025 |
Point Review - Pre-submittal Review Notes |
| 9/23/2025 |
Point Review - Pre-submittal Review Notes |
| 9/24/2025 |
Point Review - Ready for applicant submittal |
| 9/25/2025 |
Point Review - Ready for applicant submittal |
| 9/25/2025 |
Application submitted by applicant. |
| 9/25/2025 |
Point Review - Reviewed |
| 9/25/2025 |
Zoning Review - Reviewed |
| 9/25/2025 |
Plan Review - Sent to plan review |
| 9/29/2025 |
Plan Review - Reviewed |
| 9/29/2025 |
Final Review - Sent for final review |
| 10/6/2025 |
Final Review - Reviewed |
| 10/6/2025 |
Final Review - Payment Needed |
| 10/6/2025 |
Permit Issued |
| 10/6/2025 |
Final Review - Complete |
| 4/15/2026 |
Permit Renewed |
Contractors
| Name / Business |
License |
Title |
Role |
Daniel Gawrych Lunex Power Inc
Workers Comp Expired. |
CVC57085 |
Cert. Solar |
Contractor |
Daniel Gawrych Lunex Power Inc
Workers Comp Expired. |
EC13014194 |
Cert. Electrical |
Subcontractor |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Passed: Solar - Solar Final |
|
Matt Forsyth |
4/16/2026 |
| Release to power company |
|
Matt Forsyth |
4/16/2026 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
4/16/2026 |
| Release to power company |
|
Matt Forsyth |
4/16/2026 |
| Submitted Power Release through FPL Portal |
|
Ward, Emaleigh C. |
4/21/2026 |