8/18/2025
|
Application pending.
|
8/18/2025
|
City of Lake City Utilities Notified.
City of Lake City Notified of Application within Utility Service Areas LC_GAS, LC_WATER, LC_SEWER.
|
9/3/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*ADAMS WORKERS COMP-- EMAIL TO INSURANCECERT@COLUMBIACOUNTYFLA.COM
*DRIVE APPROVAL-- PENDING PAYMENT, SEE APP #72755
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
9/12/2025
|
Point Review - Ready for applicant submittal
*PLEASE LOG IN TO YOUR PORTAL AND SUBMIT APPLICATION- THIS APPLICATION WILL NOT MOVE FORWARD UNTIL IT HAS BEEN SUBMITTED
|
9/15/2025
|
Point Review - Ready for applicant submittal
*PLEASE LOG IN TO YOUR PORTAL AND SUBMIT APPLICATION- THIS APPLICATION WILL NOT MOVE FORWARD UNTIL IT HAS BEEN SUBMITTED
|
9/17/2025
|
Point Review - Ready for applicant submittal
*PLEASE LOG IN TO YOUR PORTAL AND SUBMIT APPLICATION- THIS APPLICATION WILL NOT MOVE FORWARD UNTIL IT HAS BEEN SUBMITTED
|
9/17/2025
|
Application submitted by applicant.
|
9/17/2025
|
City of Lake City Utilities Notified.
City of Lake City Notified of Application within Utility Service Areas LC_GAS, LC_WATER, LC_SEWER.
|
9/17/2025
|
Point Review - Reviewed
|
9/17/2025
|
Zoning Review - Reviewed
|
9/17/2025
|
Plan Review - Sent to plan review
|
9/17/2025
|
Plan Review - Building Approved
|
9/17/2025
|
Plan Review - Electrical Approved
|
9/17/2025
|
Plan Review - Electrical Approved
|
9/17/2025
|
Plan Review - Mechanical Approved
|
9/17/2025
|
Plan Review - Plumbing Approved
|
9/17/2025
|
Plan Review - Fuel/Gas Approved
|
9/17/2025
|
Final Review - Sent for final review
|
9/17/2025
|
Final Review - Reviewed
|
9/17/2025
|
Final Review - Payment Needed
|
9/29/2025
|
Permit Issued
Permit #000054159 created and approved.
|