Permit Details

Permit Search

Permit

Right-of-Way Access/Driveway

1809 SW BUCKLEY LN
LAKE CITY, FL 32024

Permit #
000054150
Application #
73038
Status Completed
  1. Submitted Sep 3, 2025
  2. Issued Sep 25, 2025
  3. Expires Sep 28, 2028
  4. Completed Sep 29, 2025

Property

Parcel #
09306-002
Owner
Phlc Holdings Llc, Millenia Capital Inc
Acres
9.62
Subdivision
—
Zoning
—
Flood zone
—
District
—

Permit

Status
Completed
Septic release
N/A
Related permit
Storage Building: 000054201

Job Details

Elevation regulation
Accessory Use
Finished floor requirement
Non-Habitable Structure
Fema map number
12023C0395C
Building Permit #
000054201
Status
Permanent
Type of connection for access road
Verify Existing Drive
Type of construction of property
Agricultural
Normal vehicle usage:
Automobiles;Trucks;Farm Equipment
Estimated Number of Vehicle trips per day
6
Is the access for commercial or residential use?
Residential

Status & Review History

  1. Pending applicant completion and submission.
  2. Final Review - Corrections Needed
  3. Final Review - Corrections Needed
  4. Final Review - Corrections Needed
  5. Final Review - Corrections Needed
  6. Email confirmation reminder sent.
  7. Final Review - Corrections Needed
  8. Final Review - Corrections Needed
  9. Final Review - Corrections Needed
  10. Final Review - Corrections Needed
  11. Point Review - Documents Required
  12. Final Review - Corrections Needed
  13. Application submitted by applicant.
  14. Pending Public Works Application Approval
  15. Application submitted by applicant.
  16. Pending Public Works Application Approval
  17. Application submitted by applicant.
  18. Pending Public Works Application Approval
  19. Final Review - Processing
  20. Application submitted by applicant.
  21. Pending Public Works Application Approval
  22. Final Review - Processing
  23. Final Review - Processing
  24. Application submitted by applicant.
  25. Pending Public Works Application Approval
  26. Permit Issued

Contractors

No contractors are listed on this permit.

Inspections

  1. Sep 10, 2025

    Passed: Engineering - Verify Easement Requirements

    Inspected by Chad Williams

  2. Sep 24, 2025

    Passed: Engineering - Initial Driveway

    Inspected by Smith, Blake

  3. Sep 29, 2025

    Passed: Engineering - Verify existing driveway

    Inspected by Smith, Blake

  4. Sep 29, 2025

    Cancelled: Engineering - ROW Access/Driveway connects to county maintained road

    Inspected by Nanderson