Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Commercial Construction Permit

Address 129 SW CHAD PL
LAKE CITY, FL 32025
Parcel #: 08874-001
Acres: 4.99
Owner: Hunter John B Revocable Trust Dated February 11, 2003, Hunter George D
Subdivision:
Zoning: CI
Flood Zone: X
District: 5
Application #: 70354
Permit #: 000054137
Related Permit: Site Use Approval: SITE-USE2025-086
Submitted: Tuesday, May 6, 2025
Issued: Wednesday, September 24, 2025
Expires: Sunday, May 17, 2026
Completed:
Status: Permit Issued
Septic Release? No
Notes:
*SDP 250306 ZONING APPROVAL *V-241104 PARKING VARIANCE *FINISHED FLOOR 96.0 FT SURVEYOR CONFIRMATION AT SLAB *ASSESSMENTS OWED @ PERM POWER, FINAL SEPTIC REQUIRED PRIOR TO RELEASE OF POWER *CITY TAP INSPECTION REQUIRED PRIOR TO FINAL-- REQUEST THROUGH COUNTY
LAKE CITY UTLITY CUSTOMER SERVICE NOTES 06/11/25 A tap application for water service was approved by the utility department. Locates must be obtained to ensure that the existing utility infrastructure is not damaged or obstructed.
Job Details
Finished floor requirement
Fema map number 12023C0283D
Residential or Commercial? Residential
What is the power service for? Existing Site Built Home
Other job details: generator install
Septic # (00-0000) or (X00-000) x24
Electrical Code Edition 2020 National Electrical Code
Review Notes
4/11/2025 Application pending.
5/6/2025 Application submitted by applicant.
5/6/2025 City of Lake City Utilities Notified.
5/7/2025 Point Review - Processing
5/7/2025 Zoning Review - Processing
5/7/2025 Plan Review - Documents Required
5/7/2025 Final Review - Status Cleared
5/12/2025 Plan Review - Documents Required
5/14/2025 Zoning Review - Reviewed
5/14/2025 Plan Review - Documents Required
5/14/2025 Plan Review - Documents Required
5/19/2025 Plan Review - Documents Required
6/3/2025 Plan Review - Documents Required
6/4/2025 Plan Review - Documents Required
6/6/2025 Plan Review - Documents Required
6/9/2025 Plan Review - Documents Required
6/10/2025 Plan Review - Documents Required
6/12/2025 Plan Review - Documents Required
6/16/2025 Plan Review - Documents Required
6/16/2025 Plan Review - Documents Required
6/17/2025 Plan Review - Documents Required
6/18/2025 Plan Review - Documents Required
6/23/2025 Plan Review - Documents Required
6/24/2025 Plan Review - Documents Required
6/24/2025 Plan Review - Documents Required
6/24/2025 Plan Review - Documents Required
6/26/2025 Plan Review - Documents Required
6/26/2025 Point Review - Processing
6/30/2025 Plan Review - Documents Required
7/7/2025 Plan Review - Documents Required
7/14/2025 Plan Review - Documents Required
7/20/2025 Plan Review - Documents Required
7/21/2025 Plan Review - Documents Required
7/29/2025 Plan Review - Documents Required
7/30/2025 Plan Review - Documents Required
7/31/2025 Plan Review - Documents Required
8/11/2025 Zoning Review - Reviewed
8/11/2025 Point Review - Processing
8/11/2025 Plan Review - Plumbing Approved
8/11/2025 Plan Review - Mechanical Approved
8/11/2025 Plan Review - Electrical Approved
8/11/2025 Plan Review - Building Approved
8/11/2025 Plan Review - Reviewed
8/11/2025 Final Review - Documents Required
8/13/2025 Final Review - Documents Required
8/26/2025 Final Review - Documents Required
9/1/2025 Final Review - Documents Required
9/4/2025 Final Review - Documents Required
9/8/2025 Final Review - Documents Required
9/9/2025 Final Review - Documents Required
9/10/2025 Final Review - Documents Required
9/11/2025 Final Review - Documents Required
9/14/2025 Final Review - Documents Required
9/16/2025 Final Review - Documents Required
9/21/2025 Final Review - Documents Required
9/23/2025 Final Review - Reviewed
9/23/2025 Final Review - Payment Needed
9/24/2025 Permit Issued
Contractors
Name/ Business License Title Role
Christopher Dooley
Dooley And Mack Constructors Of Georgia Inc
Liability Insurance & Workers Comp Expired.
CGC1508635 Cert. General Contractor
Benjamin L Sparks
Line Electric Company Llc
EC13009101 Cert. Electrical Subcontractor
Cody Barrs
Barrs Plumbing Inc
CFC1427145 Plumbing Contractor Subcontractor
Inspections
Inspection Notes Performed By Date
Failed: Fire - Plan Review Unable To Review Suppression System In Plans. Please Attach Plans For Approval. Cpt. Shane Overstreet 6/16/2025
Passed: Fire - Plan Review Cpt. Shane Overstreeet 7/30/2025
Release to power company Temp Pole Tcrews 10/15/2025
Passed: Electrical - Temporary Power Service Troy Crews 10/15/2025
Passed: Building - Footer Troy Crews 11/14/2025
Passed: Engineering - Setbacks Troy Crews 11/14/2025
Passed: Plumbing/Gas - 1st Underground Rough–In Troy Crews 11/18/2025