| Inspection |
Notes |
Performed By |
Date |
| Failed: Fire - Plan Review |
Unable To Review Suppression System In Plans. Please Attach Plans For Approval. |
Cpt. Shane Overstreet |
6/16/2025 |
| Passed: Fire - Plan Review |
|
Cpt. Shane Overstreeet |
7/30/2025 |
| Release to power company |
Temp Pole |
Tcrews |
10/15/2025 |
| Passed: Electrical - Temporary Power Service |
|
Troy Crews |
10/15/2025 |
| Passed: Building - Footer |
|
Troy Crews |
11/14/2025 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
11/14/2025 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
11/18/2025 |
| Passed: Building - Slab |
Reminder Have Surveyor To Do Elevation Confirmation Letter |
Troy Crews |
11/24/2025 |
| Passed: Building - Masonry Wall Reinforcing |
Add Steel To Three Spots Each Side Of Front Door Opening And Corner Of West Wall |
Troy Crews |
12/1/2025 |
| Cancelled: Building - Masonry Wall Reinforcing |
|
Tcrews |
12/2/2025 |
| Cancelled: Building - Masonry Wall Reinforcing |
|
Tcrews |
12/3/2025 |
| Passed: Building - Masonry Wall Reinforcing |
Second Partial West Wall And South Wall |
Troy Crews |
12/4/2025 |
| Passed: Building - Masonry Wall Reinforcing |
3rd Lift West And South Wall |
Troy Crews |
12/8/2025 |
| Passed: Building - Masonry Wall Reinforcing |
4th Lift On Southwest Wall And Top Out Of South Wall |
Troy Crews |
12/10/2025 |
| Passed: Building - Masonry Wall Reinforcing |
Top Out On South Wall 3rd Lift On East Wall |
Troy Crews |
12/12/2025 |
| Passed: Building - Masonry Wall Reinforcing |
Top Out Se Corner 2nd Lift East Wall |
Troy Crews |
12/15/2025 |
| Passed: Building - Masonry Wall Reinforcing |
3rd Left E Wall |
Troy Crews |
12/17/2025 |
| Passed: Building - Masonry Wall Reinforcing |
4th Lift On West And East Wall |
Troy Crews |
12/19/2025 |
| Passed: Electrical - 1st Underground Rough–In |
Main Service Conduit And Parking Lot Lights |
Troy Crews |
1/6/2026 |
| Passed: Building - Footer |
Monolithic Slab Dumpster Enclosure With Bollards |
Troy Crews |
1/12/2026 |
| Passed: Building - Rated Assembly Fastening |
Framing For Front Entryway |
Troy Crews |
1/13/2026 |
| Passed: Building - Roof Decking |
Plywood At Back Of Framing For Front Entry |
Troy Crews |
1/13/2026 |
| Passed: Building - Ext Strapping/Wall Sheathing |
Front Entryway Framing And Sheathing |
Troy Crews |
1/20/2026 |
| Passed: Building - Framing |
|
Troy Crews |
1/20/2026 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Office Area And Outside Hose Bibs |
Troy Crews |
1/23/2026 |
| Passed: Electrical - 2nd Rough-In |
Office Area And Exterior Wall Outlets |
Troy Crews |
1/23/2026 |
| Passed: Building - Framing |
Exterior Walls Hat Channel |
Troy Crews |
1/23/2026 |
| Passed: Building - Insulation |
Foam Insulation Exterior Walls Between Hat Channel |
Troy Crews |
1/23/2026 |
| Passed: Building - Footer |
Foundation Holes For Garden Center Canopy |
Troy Crews |
1/27/2026 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
1/27/2026 |
| Passed: Mechanical - Rough In |
Ductwork Office And Bathroom Areas |
Troy Crews |
2/13/2026 |
| Passed: City of Lake City Utilities - Lake City Utilities Tap Inspection |
|
City Of Lake City Distribution And Collections Department |
2/25/2026 |
| Failed: Electrical - Permanent Power |
Not Ready |
Troy Crews |
3/5/2026 |
| Passed: Electrical - Above Ceiling |
|
Troy Crews |
3/18/2026 |
| Passed: Mechanical - Framing/Fire Damper |
Mechanical Above Ceiling No Fire Dampers Required |
Troy Crews |
3/18/2026 |
| Passed: Electrical - Permanent Power |
Need Fire And Garbage Assessments And Double Check On City Water And Sewer |
Troy Crews |
3/18/2026 |
| Release to power company |
|
Mgarber |
3/20/2026 |
| Septic Release Inspection |
All Requirements Met To Release Power-- 3.20.26 Mg |
Health Dept |
3/20/2026 |