7/29/2025
|
Application pending.
|
7/30/2025
|
Point Review - Pre-submittal Review Notes
NEEDED
* LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE
* FLOODPLAIN NOTICE TO OWNER
* PROPERTY APPRAISER DETAIL SHEET (FIND THIS ON PROPERTY APPRAISERS WEBSITE)
* MG VERIFY ADDRESS POINT IS CORRECT
* ARCHITECT/ENGINEER NAME AND ADDRESS CELL TO BE COMPLETED
* drive app to be completed - verify existing
|
8/2/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE
*FLOODPLAIN NOTICE TO OWNER
|
8/5/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE
*FLOODPLAIN NOTICE TO OWNEr
|
8/7/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE
*FLOODPLAIN NOTICE TO OWNER
|
8/7/2025
|
Zoning Review - Reviewed
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE
*FLOODPLAIN NOTICE TO OWNER
zoning: Structure is in a Special Flood Hazard Area, Flood Zone A. Structure to remain open to allow for water to flow in and out and will not be closed in to become a part of the MH.
|
8/11/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE
*FLOODPLAIN NOTICE TO OWNER
ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
8/13/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE-- FORM UPLOADED IS FILLED OUT INCORRECTLY
ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
8/26/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE-- FORM UPLOADED IS FILLED OUT INCORRECTLY
ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
8/28/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE-- FORM UPLOADED IS FILLED OUT INCORRECTLY
ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/1/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE-- FORM UPLOADED IS FILLED OUT INCORRECTLY
ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/9/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE-- LOA SHOULD HAVE STEVEN LISTED IN FIRST BLANK, JAIMEE LISTED IN THE 2ND BLANK, AND SIGNED BY STEVEN
ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/10/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE-- LOA SHOULD HAVE STEVEN LISTED IN FIRST BLANK, JAIMEE LISTED IN THE 2ND BLANK, AND SIGNED BY STEVEN
ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/11/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE-- LOA SHOULD HAVE STEVEN LISTED IN FIRST BLANK, JAIMEE LISTED IN THE 2ND BLANK, AND SIGNED BY STEVEN
ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/15/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE-- LOA SHOULD HAVE STEVEN LISTED IN FIRST BLANK, JAIMEE LISTED IN THE 2ND BLANK, AND SIGNED BY STEVEN
ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/17/2025
|
Point Review - Pre-submittal Review Notes
NEEDED:
*LAND OWNER AFFIDAVIT FROM STEVEN TO JAIMEE-- LOA SHOULD HAVE STEVEN LISTED IN FIRST BLANK, JAIMEE LISTED IN THE 2ND BLANK, AND SIGNED BY STEVEN
ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/21/2025
|
Point Review - Ready for applicant submittal
*PLEASE LOG IN TO YOUR PORTAL AND SUBMIT APPLICATION- THIS APPLICATION WILL NOT MOVE FORWARD UNTIL IT HAS BEEN SUBMITTED
***ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/22/2025
|
Application submitted by applicant.
|
9/22/2025
|
Point Review - Reviewed
***ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/22/2025
|
Zoning Review - Reviewed
***ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/22/2025
|
Plan Review - Sent to plan review
***ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/23/2025
|
Plan Review - Building Approved
***ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/23/2025
|
Plan Review - Reviewed
***ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/23/2025
|
Final Review - Sent for final review
***ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/23/2025
|
Final Review - Reviewed
***ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/23/2025
|
Final Review - Payment Needed
***ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|
9/23/2025
|
Permit Issued
Permit #000054126 created and approved.
|
9/23/2025
|
Final Review - Complete
***ZONING: STRUCTURE IS IN A SPECIAL FLOOD HAZARD AREA, FLOOD ZONE A. STRUCTURE TO REMAIN OPEN TO ALLOW FOR WATER TO FLOW IN AND OUT AND WILL NOT BE CLOSED IN TO BECOME A PART OF THE MH CONDITIONED SPACE.
|