Permit Details

Permit Search

Permit

Mobile Home

301 NE CEMETERY LOOP
LAKE CITY, FL 32055

Permit #
000054110
Application #
72936
Status Completed
  1. Submitted Aug 27, 2025
  2. Issued Sep 22, 2025
  3. Expires Aug 31, 2026
  4. Completed Apr 8, 2026

Property

Parcel #
04667-001
Owner
4 Guys Investments Llc,
Acres
4.37
Subdivision
—
Zoning
A-3
Flood zone
X
District
1

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
Bottom of lowest beam must be one foot above the road
Fema map number
12023C0205D
Mobile Home is a:
Double Wide
Year Built
2023
Width (Ft.In)
32
Length (Ft.In)
72
Driveway access to home:
Private Driveway Permit
Installation Decal #
10794
Septic #
25-0699
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Are you applying for a 5 year temporary permit?
No
Serial #
520992AB
Wind Zone?
2
Residential or Commercial Use?
Residential
Service Amps
200
How many of bedrooms does this home have?
5
How many bathrooms does this home have?
2

Status & Review History

  1. Application pending.
  2. Point Review - Pre-submittal Review Notes
  3. Point Review - Pre-submittal Review Notes
  4. Point Review - Pre-submittal Review Notes
  5. Point Review - Pre-submittal Review Notes
  6. Point Review - Ready for applicant submittal
  7. Application submitted by applicant.
  8. Point Review - Reviewed
  9. Zoning Review - Reviewed
  10. Plan Review - Reviewed
  11. Final Review - Reviewed
  12. Final Review - Payment Needed
  13. Permit Issued
  14. Final Review - Complete
  15. Permit Status Update Notification

Contractors

  • Robert D Sheppard

    Robert Sheppard Mobile Home Set Up Llc

    License
    IH1025386
    Title
    Mh Installer (ih)
    Role
    Contractor

    County License & Liability Insurance Expired.

Inspections

  1. Mar 4, 2026

    Passed: Mobile Home - Mobile Home Set-Up Final

    Final Septic Required Prior To Release Of Power & Co-- 4.2.26 Mg

    Inspected by Troy Crews

  2. Mar 4, 2026

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Apr 23, 2026

    Release to power company

    Inspected by Ewilliams

  4. Apr 23, 2026

    Septic Release Inspection

    Inspected by Health Dept

  5. May 1, 2026

    Release to power company

    Inspected by Ewilliams