| Inspection |
Notes |
Performed By |
Date |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Michael Williams |
10/9/2025 |
| Passed: Building - Monolithic Slab |
|
Michael Williams |
10/14/2025 |
| Passed: Engineering - Setbacks |
|
Michael Williams |
10/14/2025 |
| Passed: Private Provider - Private Provider Inspection |
Wall Sheathing Passed By Michael Williams |
Garber, Melissa |
10/29/2025 |
| Passed: Private Provider - Private Provider Inspection |
Roof Decking Passed By Michael Williams |
Garber, Melissa |
10/29/2025 |
| Passed: Private Provider - Private Provider Inspection |
Utility Pole Final Passed By Michael Williams |
Garber, Melissa |
11/3/2025 |
| Passed: Private Provider - Private Provider Inspection |
Rated Assembly Fastening Passed By Michael Williams |
Garber, Melissa |
11/3/2025 |
| Passed: Private Provider - Private Provider Inspection |
Roof In Progress Passed By Michael Williams |
Garber, Melissa |
11/3/2025 |
| Passed: Building - Framing |
Framing Passed By Michael Williams |
Garber, Melissa |
11/13/2025 |
| Passed: Building - Insulation |
Insulation Passed By Michael Williams |
Garber, Melissa |
11/13/2025 |
| Passed: Private Provider - Private Provider Inspection |
Electrical - 2nd Rough In Passed By Michael Williams |
Garber, Melissa |
11/13/2025 |
| Passed: Private Provider - Private Provider Inspection |
Mechanical - Rough In Passed By Michael Williams |
Garber, Melissa |
11/13/2025 |
| Passed: Private Provider - Private Provider Inspection |
Plumbing/gas - 2nd Rough In Passed By Michael Williams |
Garber, Melissa |
11/13/2025 |
| Passed: Electrical - Temporary Power Service |
|
Pp Michael Williams |
12/3/2025 |
| Release to power company |
|
Ewilliams |
12/11/2025 |
| Release to power company |
Re-release Power Notice |
Nanderson |
12/11/2025 |
| (Requested) Building-Roof Decking |
|
|
|
| (Requested) Building-Wall Sheathing |
|
|
|